CDOT to Install Median Barriers on I-70 to 2027

The Colorado Department of Transportation starts a $3.48 million cable barrier project on Interstate 70 between Watkins and Bennett on November 19.

Updated on Nov. 17, 2026 in Automotive

Photograph of a long median cable barrier line receding across dry prairie grass beside an empty interstate under low morning sun.
The Colorado Department of Transportation begins a $3.48 million project on November 19 to install median cable barriers along 13.8 miles of Interstate 70 between Watkins and Bennett. AI Illustration. Upload story photo >

The Colorado Department of Transportation begins a $3.48 million project to install and improve median cable barriers on a 13.8-mile stretch of Interstate 70 between Watkins and Bennett, starting Thursday, November 19, 2026. Construction will close lanes and shoulders on weekdays and Saturdays while crews work.

Why it matters

The barriers are intended to keep vehicles from crossing the median into oncoming traffic and to reduce the severity of crashes and head-on collisions. Motorists on this corridor in Adams and Arapahoe counties should expect lane closures throughout the work.

The $3.48 million project spans 13.8 miles of Interstate 70 and includes nine cable-barrier sections. Crews will re-grade the median to flatter, more uniform slopes and install a concrete strip to control vegetation.

The players

Colorado Department of Transportation

The state agency responsible for planning, building and maintaining Colorado's highway system, including Interstate 70.

The details

Work begins just east of Bennett and moves west toward Watkins, with crews installing the cable-barrier sections one at a time. Weekday work closes one westbound lane and the eastbound shoulder from 9 a.m. to 5 p.m., while Saturday work closes one lane in each direction and the westbound shoulder from 7 a.m. to 6 p.m.

Timeline

  1. Thursday, November 19, 2026: Construction begins east of Aurora.

  2. Late March 2027: Project expected to be completed.

Roadmap

Cable median barriers are a widely used technology on divided interstates to stop cross-median crashes, and this project extends that approach along a long Interstate 70 corridor east of Denver. It fits a broader state pattern of adding median protection to high-crash rural and suburban freeway segments.

Drivers on Interstate 70 between Watkins and Bennett will face lane and shoulder closures on weekdays from 9 a.m. to 5 p.m. and on Saturdays from 7 a.m. to 6 p.m. Plan extra travel time through the work zone until the project wraps up in late March 2027.

The takeaway

Median cable barriers are designed to separate opposing traffic and reduce head-on crash severity, so drivers should expect slower speeds and lane shifts through the work zone. Allow extra time for trips on this stretch of Interstate 70 until construction is complete.

What happens next

Construction is expected to finish by late March 2027, with weekday and Saturday lane closures continuing until then.