Union City Advances Capital Improvement Projects

City public works updated the council on road, transit, and facility projects, including a bus lane, a permanent I Street closure, and park upgrades.

Updated on Nov. 3, 2026 in Openings & Closings

Screen-print poster illustration of a painted teal bus lane curving along an empty road beside a concrete median and bare light poles under soft daylight.
Union City public works told the city council on October 27 about a part-time bus lane near James Logan High School and a permanent closure of I Street near the BART station. AI Illustration. Upload story photo >

Union City's public works department announced capital improvement project updates to the city council on October 27. The plans include a part-time bus lane near James Logan High School, a permanent I Street closure near Union City BART, and renovations to city facilities.

Why it matters

The projects will change traffic patterns, transit access and public facilities across Union City over the next several years. Residents near the affected roads, the BART station and local fields and workshops will see construction and new routines as the work proceeds.

The Quarry Lakes Parkway project would include three car lanes, and the bus lane near James Logan High School would run during 7 to 9am and 2 to 6pm peak periods. Specific project costs and funding amounts were not provided in the update.

The players

Union City Public Works Department

The municipal department responsible for planning, building and maintaining Union City's streets, facilities and infrastructure projects.

Union City Council

The elected legislative body of Union City that reviews and approves city projects, budgets and policy.

The details

Public works plans a bus lane with pavement markings and signs indicating buses-only times near James Logan High School. The I Street closure near Union City BART would be permanent and would allow the east BART entrance to open, replacing the railroad safety gates currently in place. The Larry Orozco Teen Workshop is undergoing environmental hazard abatement for lead, asbestos and mold, while the Shorty Garcia soccer fields are receiving stadium light improvements, and a BART mural project is underway with city staff planning to clean columns and secure permits.

Timeline

  1. October 27: Public works presented capital improvement updates to the city council.

  2. Early 2027: The part-time bus lane is projected to begin operating during peak hours.

  3. December 2027: Larry Orozco Teen Workshop renovations are projected to be finished.

  4. Late 2027 to late 2028: The I Street BART project completion window.

  5. End of 2028: Quarry Lakes Parkway is expected to be completed and open.

Market Landscape

The I Street closure and east BART entrance fit into a broader pattern of cities reworking station access to support transit-oriented development. The bus lane and multimodal Quarry Lakes Parkway similarly reflect a shift toward street designs that serve transit, cyclists and pedestrians alongside cars.

Drivers and bus riders near James Logan High School will face peak-hour bus-only restrictions once the lane opens. Residents near Union City BART will lose the I Street crossing permanently but gain an east-side station entrance.

The takeaway

Residents who commute near James Logan High School, Union City BART or Quarry Lakes Parkway should plan for construction and new traffic patterns over the next two years. Checking city council updates will show schedule changes as projects advance.

What happens next

The part-time bus lane is projected to begin operating in early 2027, and the I Street BART project has a completion window from late 2027 to late 2028.