Tracy Approves $5.65M Increase for Interchange
The Tracy City Council unanimously approved additional funding for the I-580/Patterson Pass interchange project, which is about 70% complete.
Updated on Nov. 27, 2026 in Construction

Live Poll
Do you trust your local government to keep big road projects on budget?
The Tracy City Council voted unanimously on November 17 to approve $5.65 million in additional funding for the I-580/Patterson Pass interchange project. The increase brings the project budget to close to $67.5 million.
Why it matters
The added funding keeps the interchange project moving as it nears completion, affecting traffic flow and infrastructure spending for residents of Tracy. The cost increase reflects unexpected field conditions, extensive utility coordination, and design refinement.
The $4 million contingency increase and $1.65 million construction management increase make up the $5.65 million approval, with the project about 70% complete. The city's $24.9 million state grant and roughly $25 million from the Tracy Infrastructure Master Plan Fund are among the project's funding sources.
The players
O.C. Jones & Sons
A Berkeley-based construction firm holding the main contract for the I-580/Patterson Pass interchange project.
Dewberry Engineers Inc.
A Manteca-based engineering firm providing construction management services for the interchange project.
Tracy City Council
The elected governing body of the City of Tracy that voted unanimously to approve the additional project funding.
The details
The increase includes $4 million for the construction contingency fund and $1.65 million for the construction management contract, with the contingency fund rising from nearly $6.4 million to nearly $10.4 million. O.C. Jones & Sons holds the main construction contract, originally approved in June 2024 at nearly $42.6 million, while Dewberry Engineers Inc. holds the construction management contract, now just over $6 million.
Timeline
2020: City secured a $24.9 million Trade Corridor Enhancement Program grant
June 2024: Council originally approved the O.C. Jones & Sons construction contract
October 12, 2025: Finance Committee recommended a $5.56 million appropriation and interfund loan
October 20, 2025: Council approved a $4.6 million transfer from general fund reserves
November 17, 2025: Council unanimously approved the $5.65 million cost increase
Market Landscape
The interchange draws on a blend of state grants, city reserves, and the Tracy Infrastructure Master Plan Fund, which together fund the roughly $67.5 million project. The contingency increase reflects how large public road projects often absorb cost growth from field conditions and utility coordination.
Drivers using I-580 and Patterson Pass Road will face traffic shifts as the new ramp layout opens in late October, subject to weather. The interchange is expected to open in spring 2027, relieving congestion once construction is finished.
The takeaway
Large public road projects often grow in cost as unexpected conditions and utility work emerge, so budget increases of this kind are a common feature of major infrastructure. Residents can track the interchange's progress as the spring 2027 opening approaches.
What happens next
The new interchange is expected to open in spring 2027, and traffic is expected to shift to a new ramp layout in late October, with timing subject to weather changes.
Further reading
Explore more local projects in Construction coverage for Tracy.
Source note: This article includes information reported by Hoodline.
Live Poll
Do you trust your local government to keep big road projects on budget?