Santa Monica Approves $2.4M Virginia Park Playground
The City Council awarded a design-build contract to Landscape Structures Inc. to replace the aging Pico neighborhood playground.
Updated on Nov. 24, 2026 in City Hall

Live Poll
Do you think your city spends public money on local parks wisely?
The Santa Monica City Council approved a design-build contract worth up to $2,399,834 with Landscape Structures Inc. to replace the playground at Virginia Avenue Park on November 17. The contract includes a $200,000 contingency and is funded through federal Community Development Block Grant dollars and the city's Special Revenue Fund.
Why it matters
The playground was installed during the park's 2005 renovation and was identified by city staff as a priority due to deteriorating equipment and limited accessibility. The project addresses aging recreational infrastructure in the Pico neighborhood while relying on federal grant funding for a large share of the cost.
The contract totals up to $2,399,834, including a $200,000 contingency, with $1,207,834 drawn from federal Community Development Block Grant funds. Of the total, $899,834 in future-year funding remains subject to City Council budget approval.
The players
Santa Monica City Council
The elected legislative body of the City of Santa Monica, California, which approves city contracts, budgets, and capital projects.
Landscape Structures Inc.
A playground equipment manufacturer and design-build firm that designs and constructs public play spaces.
The details
The council selected Landscape Structures Inc. through a competitive procurement that drew two proposals, while Curious Creative was deemed nonresponsive because its submission offered design services without construction capabilities. The council also approved a categorical exemption under the California Environmental Quality Act, and city staff reported that no trees are currently slated for removal.
Timeline
Nov. 17, 2026: City Council approves the design-build contract with Landscape Structures Inc.
Fiscal year 2026-27: $1.5 million allocated under the financial plan.
Early 2027: Design work expected to begin.
Late summer 2028: Construction scheduled for completion.
Political Context
The council relied on a categorical exemption under the California Environmental Quality Act, which covers replacement of existing facilities, instead of undertaking a full environmental review. The approach mirrors how many California cities handle like-for-like park upgrades, with opposition typically centered on tree removal and construction impacts rather than the exemption itself.
Residents who use Virginia Avenue Park can expect the existing playground to be closed while it is replaced, with the new equipment not scheduled to open until late summer 2028. The project is funded primarily by federal and city park fees rather than new general taxes, so the direct cost to households is not changed by the contract itself.
The takeaway
Replacing aging park equipment is a multi-year process that combines grant money, city fees and council budget approvals, so the timeline for a finished playground runs well past the contract vote itself.
What happens next
Design work is expected to begin in early 2027, with construction scheduled for completion in late summer 2028.
Further reading
Explore more council decisions in the City Hall section for context on how Santa Monica funds local projects.
Source note: This article includes information reported by Patch.
Live Poll
Do you think your city spends public money on local parks wisely?






