San Rafael Approves Safety Upgrades for City Intersection
The city council authorized a $3.5 million plan to reconfigure a busy junction to improve safety for pedestrians.
Updated on Oct. 27, 2026 in Construction

Live Poll
Should city traffic projects prioritize road safety over the convenience of local neighborhood access?
San Rafael officials have approved a $3.5 million traffic safety project for the intersection of Second and Fourth streets. The redesign aims to protect pedestrians and cyclists by adding a refuge island and shortening crossing distances.
Why it matters
The project addresses concerns regarding an intersection that sees more than 20,000 vehicles daily and has been deemed by city staff to be at the end of its useful life. Despite a petition signed by 106 residents requesting the rejection of the plan, officials moved forward to improve safety for all commuters.
The council awarded a $2.87 million construction contract to Ghilotti Bros. Inc. and a $573,908 management contract to Consor. The project budget is largely supported by $3 million in grant funding.
The players
Ghilotti Bros. Inc.
This construction firm was awarded the $2.87 million contract to perform the physical infrastructure improvements at the intersection.
Consor
This engineering firm was contracted by the city for $573,908 to provide management services for the construction project.
Marin Municipal Water District
This utility provider is currently conducting water line replacement work that must be finished before intersection construction begins.
Victoria DeWitt
A local resident who testified before the San Rafael City Council regarding the proposed intersection changes.
The details
The plan involves removing a left turn lane from westbound Second Street onto Marquard Avenue to accommodate a new pedestrian refuge island. The construction will be executed in five phases over four months once the water line replacement work in the area concludes.
Timeline
Construction is expected to take place over a four-month period.
Marin Municipal Water District water line work began in October 2026.
Resident Victoria DeWitt testified before the City Council on October 19, 2026.
Market Landscape
This project follows a pattern of recent city infrastructure investments established by the $20.8 million Third Street overhaul. It reflects a broader shift toward reallocating municipal resources to prioritize multi-modal safety over standard vehicular throughput.
Residents should anticipate phased roadwork lasting four months once the current water line replacement project concludes. These changes will permanently alter driving patterns at the intersection of Second and Fourth streets by removing a previously available left turn lane.
The takeaway
City planners are increasingly prioritizing pedestrian and cyclist safety through intersection reconfigurations despite resident opposition. Drivers in San Rafael should stay informed on upcoming traffic pattern changes as the city completes this multi-phase safety upgrade.
Further reading
Learn more about local development in our Construction section.
Source note: This article includes information reported by Marin Independent Journal.
Live Poll
Should city traffic projects prioritize road safety over the convenience of local neighborhood access?