Crews to Demolish San Onofre Reactor Domes in 2027

Exterior demolition of the decommissioned plant's domes is expected to begin next year after wastewater releases in late 2026.

Updated on Nov. 18, 2026 in Nuclear

Crews to Demolish San Onofre Reactor Domes in 2027

Live Poll

Do you trust the cleanup of the San Onofre nuclear plant to be handled safely?

Crews are expected to begin exterior demolition of the San Onofre Nuclear Generating Station domes in 2027, with both units expected to be fully dismantled by 2028. The project, about 90% complete as of Nov. 5, 2026, has seen two unintended wastewater releases, on Sept. 23 and Nov. 3, 2026, with pH levels exceeding permit limits.

Why it matters

The plant opened in 1968 and its units have been offline since 2012, and roughly 1,600 metric tons of spent nuclear fuel will remain on-site in steel canisters until the federal government identifies a location to move it. The wastewater incidents raise questions about how decommissioning work is being monitored and controlled in San Clemente and along the surrounding coast.

The operator reported the project at about 90% complete as of Nov. 5, 2026, while two wastewater releases in September and November exceeded pH permit limits. Whether the regional board will take further action on the releases has not been reported.

The players

San Onofre Nuclear Generating Station

The Southern California nuclear plant opened in 1968 near San Clemente and has been undergoing decommissioning since its Units 2 and 3 went offline in 2012.

San Onofre Decommissioning Solutions

The contractor overseeing the dismantling of the San Onofre plant is carrying out demolition and wastewater management work at the site.

San Diego Water Quality Control Board

The regional state agency that regulates water quality in San Diego County was notified of the pH exceedances tied to the plant's wastewater releases.

The details

Interior demolition of Unit 3 is underway, and crews will release about 1 million gallons of treated groundwater in batches after adjusting pH and ensuring suspended solids meet regulatory limits. A basement wall below the water table was breached, and notifications about the pH exceedances were sent to the San Diego Water Quality Control Board.

Timeline

  1. Sept. 23, 2026: About 5,000 gallons of wastewater discharged offshore from Unit 2's storm drain system.

  2. Nov. 3, 2026: A hose failure spilled 900 gallons of wastewater onto asphalt.

  3. Nov. 5, 2026: A Community Engagement Panel meeting was held as the project was reported 90% complete.

  4. 2027: Exterior demolition of both units is expected to begin.

  5. 2028: Dismantling of both units is expected to be finished.

The Big Picture

Decommissioning at San Onofre is advancing while roughly 1,600 metric tons of spent fuel stay on-site until the federal government finds a destination for it. The wastewater incidents show that dismantling the plant's structures carries environmental control challenges even as demolition timelines move forward.

Residents near San Clemente and the coast should watch for official notices from the San Diego Water Quality Control Board about wastewater discharges during demolition. Anyone concerned about the releases can contact the regional board directly to request information about monitoring and permit compliance.

The takeaway

Decommissioning a nuclear plant involves long timelines and ongoing environmental monitoring, and the spent fuel will remain on-site until a federal storage location is chosen. Readers following the project can track the 2027 demolition start and 2028 completion target for updates.

What happens next

Crews are expected to begin exterior demolition of both units in 2027 and finish dismantling them in 2028.

Further reading

For background on the plant's long-running shutdown, see the Nuclear coverage on Wisevoter.

Source note: This article includes information reported by The Coast News.