SMUD Board Weighs Data Center Cost Rules
Protesters gathered outside SMUD headquarters as the board discussed principles requiring large load customers to bear their own service costs.
Updated on Nov. 19, 2026 in Data Centers

Live Poll
Do you think the data center boom is making your area a worse place to live?
About 60 to 70 demonstrators gathered at 6201 S St. before a Wednesday, Nov. 11 Board Policy Committee meeting, and the board took no action. The proposed principles would require customers needing more than 50 megawatts to bear the costs and risks of their service.
Why it matters
The proposal aims to direct costs onto large load customers rather than residential or commercial ratepayers. Local governments approve data center projects, and SMUD must serve them once approved, so the cost rules shape who pays as development grows in the region.
The proposed threshold of 50 megawatts is set against an 18-megawatt data center approved by Sacramento County at McClellan Park, which drew no public input. Whether the principles will be adopted, and how costs will be divided, remains unresolved.
The players
Sacramento Municipal Utility District (SMUD)
SMUD is the publicly owned electric utility serving the Sacramento region, governed by an elected board of directors.
The details
SMUD reported in September that it reviewed one proposal for a data center project, which drew controversy after it was approved without a public vote. The proposed principles require large customers to show they can cover project costs through financial and contractual agreements before SMUD takes on significant obligations.
Timeline
September: SMUD reported reviewing one data center project proposal.
Wednesday, Nov. 11: Demonstrators gathered outside SMUD headquarters; the board took no action.
Thursday: The board was scheduled to vote on the proposed principles, but the vote was later postponed.
The Tech Race
The Sacramento debate follows Oakland's extended one-year data center moratorium and Fresno's move to draft a 10-year ban on such facilities. Together, these local actions signal growing scrutiny of how data center expansion is financed and approved.
If adopted, the principles would place the cost and risk of large-scale power service on data center developers rather than on residential and small business customers. Sacramento-area ratepayers would see the outcome in future utility bills and service decisions.
The takeaway
Utility cost rules for large power users can shape household bills as data center demand grows. Readers should watch for the board's eventual vote on the principles.
Further reading
Explore more coverage in Data Centers for context on how local utilities are handling large-scale power demand.
Source note: This article includes information reported by The State Hornet.
Live Poll
Do you think the data center boom is making your area a worse place to live?






