Riverside to Hold Third Street Underpass Meeting
The December 2 community session will cover the $93.5 million project to lower Third Street and build a rail underpass.
Updated on Nov. 28, 2026 in City Hall

Live Poll
Should Riverside spend $93.5 million to build the Third Street underpass?
Riverside will host a community meeting on the Third Street Grade Separation project on Wednesday, December 2, from 6 to 8 p.m. at John W. North High School. The project would lower Third Street between Vine Street and Park Avenue to build a rail underpass with an estimated cost of $93.5 million.
Why it matters
Nearly 100 trains pass through downtown Riverside each day, blocking Third Street for roughly three hours and 12 minutes out of every 24 hours. The project is intended to eliminate the at-grade crossing and reduce the disruption to traffic and emergency response along the corridor.
The project carries an estimated cost of $93.5 million, and a $3 million request to Rep. Mark Takano was approved to help fund construction. Without intervention, daily traffic stoppages along the corridor are projected to reach about 10 hours a day by 2046, though the source does not detail how remaining funding will be secured.
The players
Riverside County Transportation Commission
The county agency responsible for regional transportation planning and funding that oversees projects of this kind across Riverside County.
Rep. Mark Takano
The U.S. House representative for the region whose office approved a $3 million funding request to help support construction of the project.
The details
The project would replace the at-grade crossing with a new bridge carrying railroad tracks over Third Street, creating a four-lane underpass for vehicles, cyclists and pedestrians. The site lies southwest of the 91/215 freeway interchange, and the underpass is expected to cut emergency response times.
Timeline
Summer 2024: Final design was earlier projected to be completed.
Spring 2025: Construction contracts were earlier projected to be awarded.
December 2, 2026, 6 to 8 p.m.: Community meeting at John W. North High School.
January 2027: Construction is anticipated to start.
December 2028: Construction and the underpass are anticipated to be completed.
City Hall Context
The project's own traffic projections show daily Third Street stoppages growing toward about 10 hours a day by 2046 without intervention, which the underpass is designed to prevent. The approved $3 million federal request signals that the project is drawing outside funding alongside local planning.
Residents who travel Third Street or the downtown corridor could see daily blockages reduced once the underpass is complete, which the project expects to shorten emergency response times. The December 2 meeting at John W. North High School gives the public a direct opportunity to review the plan before construction begins.
The takeaway
Daily train blockages on Third Street are a recurring problem that the underpass is designed to solve permanently. Attending the December 2 meeting is the most direct way for residents to weigh in before construction starts in January 2027.
What happens next
A community meeting on the Third Street Grade Separation project will be held Wednesday, December 2, 2026, from 6 to 8 p.m. at John W. North High School, with construction anticipated to begin in January 2027.
Further reading
For more on local government projects and public meetings, see City Hall coverage in Riverside.
Source note: This article includes information reported by Hoodline.