Rancho Cordova Approves Bridge Contract Increase
The city council authorized an additional $2.2 million to support the Zinfandel Drive pedestrian overcrossing project.
Updated on Oct. 20, 2026 in Remote Work

Live Poll
Should local governments approve additional funding when infrastructure projects exceed their original budget?
The Rancho Cordova City Council approved a $2.2 million contract increase for the Zinfandel Drive Bicycle and Pedestrian Overcrossing Project on October 19, 2026. This funding adjustment raises the total project budget to $38.2 million.
Why it matters
The cost increase stems from extensive delays in securing necessary state approvals. The project complexity and scale necessitated additional engineering assistance, artist coordination, and management of state agency reviews.
The total project cost is $38.2 million, bolstered by $23.3 million in state and federal funding. The project scope includes a $1.4 million art walk.
The players
Rancho Cordova City Council
This is the primary legislative body responsible for overseeing the city budget and municipal infrastructure projects in Rancho Cordova.
Dewberry Engineers Inc.
This is the engineering firm contracted by the city to provide technical assistance, artist coordination, and agency review management.
The details
The contract with Dewberry Engineers Inc. now covers expanded engineering, artist coordination, and management of state agency reviews. The council approved the funding boost through a consent calendar vote.
Timeline
February 2020: City awarded an initial $3.1 million contract to Dewberry Engineers Inc.
December 2025: City added $965,000 to the existing engineering contract.
October 19, 2026: City Council approved the latest $2.2 million contract increase.
Spring 2027: Construction is tentatively scheduled to begin.
Fall 2027: Construction is tentatively scheduled to conclude.
Market Landscape
Public infrastructure projects like the Zinfandel Drive Bicycle and Pedestrian Overcrossing Project often face significant cost escalations due to the complexity of regulatory compliance. This funding adjustment reflects the common industry struggle to balance scale with state-level administrative demands.
The bridge project is a long-term development effort, but local residents should note that construction timelines remain set for 2027. Future project updates will be critical for those commuting near Zinfandel Drive and Folsom Boulevard.
The takeaway
Large-scale public projects frequently encounter cost overruns due to extended timelines in state-level oversight and agency approvals. Residents can monitor future council meetings to track how these added funds impact final project delivery in 2027.
Further reading
For more information on local infrastructure, visit the Remote Work section.
Source note: This article includes information reported by The Sacramento Bee.