Pleasanton Starts Replacing 22,000 Water Meters

The $12 million project will replace aging meters that have failed across the city's water system.

Updated on Nov. 12, 2026 in Business

Round cast-iron water meter lid in dry grass beside a concrete curb, with copper pipes visible in the open meter pit below.
Pleasanton began replacing more than 22,000 aging water meters in November, a $12 million project to fix billing errors and water loss. AI Illustration. Upload story photo >

Live Poll

Do you think Pleasanton's water service is getting better or worse for households?

Pleasanton began replacing more than 22,000 water meters at homes and businesses in November 2026. The city says widespread failures in its meter and Advanced Metering Infrastructure system led to billing inaccuracies, increased water loss and rising operational costs.

Why it matters

The project aims to improve aging infrastructure so water customers are not overcharged and the city's water system is strengthened. Residents in Pleasanton will see the work take place block by block over the coming months.

The project is funded by the Water Enterprise Fund, water revenue bond proceeds and revenue from increased water rates, with a total cost of about $12 million. The source does not say how these funding sources will be split.

The players

Pleasanton Mayor Jack Balch

Jack Balch is the mayor of Pleasanton, California, a city in the East Bay region.

Concord Utility Services

Concord Utility Services is a contractor that is replacing water meters in Pleasanton starting in November 2026.

Core & Main LP

Core & Main LP is a company that is carrying out the water meter replacement work in Pleasanton alongside Concord Utility Services.

The details

Core & Main LP and Concord Utility Services will carry out the work, beginning in south Pleasanton and moving through zones laid out by the city. Customers receive advance notice, and water service will be shut off for about 30 minutes on installation day.

Timeline

  1. June 16, 2026: City council received a staff report on meter failures.

  2. November 5, 2026: The city issued a press release announcing the project.

  3. November 2026: Meter replacement work began in south Pleasanton.

  4. May 2027: Replacement work is expected to be completed.

Roadmap

The project is one step within the city's 20-year Water System Management Plan, which addresses aging water infrastructure. Replacing meters now is intended to prevent further billing errors and water loss as the system ages.

Residents will receive advance notice before their meter is replaced and should expect about 30 minutes without water on installation day. Customers can track their water use and receive leak alerts through the MyWater Pleasanton app and online portal.

The takeaway

Check your MyWater Pleasanton account for leak alerts and usage data once your new meter is installed. Watch for advance notices so you can plan around the brief water shutoff.

What happens next

Concord Utility Services is expected to begin replacing water meters in November 2026, with completion expected around May 2027.

Further reading

Explore more Pleasanton Utilities coverage to see how local water and energy systems are managed.

More information

Find the timeline and details on the city water meter replacement project on the City of Pleasanton website.

Source note: This article includes information reported by Pleasanton Weekly.