Pasadena Approves $111 Million Federal Water Loan

The City Council unanimously approved a federal WIFIA loan to fund $226.6 million in water system upgrades.

Updated on Nov. 13, 2026 in Utilities

Wide photograph of an open trench beside stacked gray water pipes and a low concrete reservoir wall under clear daylight in a dry hillside setting.
The Pasadena City Council unanimously approved a $111 million federal WIFIA loan on Monday to help fund $226.6 million in water system upgrades, led by the $95.8 million Sunset Reservoir Complex. AI Illustration. Upload story photo >

Live Poll

Would you support your city borrowing federal money to upgrade the water system?

Pasadena City Council unanimously approved a $111 million loan through the U.S. Environmental Protection Agency's WIFIA program to help fund $226.6 million in water system improvements. The largest project is the $95.8 million Sunset Reservoir Complex.

Why it matters

The Sunset Reservoir is a key part of Pasadena's water system, and the upgrades will help the city tap groundwater from the Raymond Basin during droughts or when imported supplies are limited. The loan covers up to 49% of total project costs.

The loan carries an estimated 5.5% interest cost, with roughly $356.5 million in principal and interest expected over its life, and payments of about $11.6 million a year beginning in 2038. Whether the projected savings over a municipal bond plan will fully materialize has not been confirmed.

The players

U.S. Environmental Protection Agency

The federal agency administers the WIFIA program that provides the low-cost loan financing for the Pasadena water projects.

Pasadena Water and Power

The city utility plans and oversees the $226.6 million in water system improvements funded partly by the loan.

PFM Financial Advisors

The financial advisory firm received an additional $100,000, bringing its total city contract to $350,000.

The details

The city can borrow as construction progresses rather than taking the full amount upfront, and it can pay off the loan early without penalty. The projects include replacing about 15 miles of aging water mains, replacing roughly 18,000 water meters and upgrading another 20,000.

Timeline

  1. Loan payments are not expected to begin until June 2037.

  2. Annual payments are expected to reach about $11.6 million starting in 2038.

Market Landscape

Pasadena's use of the federal WIFIA program follows a model in which cities borrow from the U.S. Environmental Protection Agency at lower cost than traditional municipal bonds to replace aging water infrastructure. The approach is meant to let local utilities finance large capital projects while spreading repayment over decades.

Pasadena residents may see the effects of the water upgrades through replaced mains and meters, though the stub does not say whether rates will change. The loan's repayment schedule begins in 2037, meaning the financing cost will be carried by the city's water system over the long term.

The takeaway

Large water infrastructure projects often depend on long-term federal financing, and Pasadena's approach shows how cities can reduce borrowing costs while building drought resilience. Residents may benefit from more reliable water service once the upgrades are complete.

Further reading

Explore more local coverage in Utilities for related water and infrastructure developments.

Source note: This article includes information reported by Pasadena Now.

Live Poll

Would you support your city borrowing federal money to upgrade the water system?