Crews Near Final Stages of South Palm Canyon Bridge

The replacement of the 1930 South Palm Canyon Bridge over Tahquitz Creek is nearing completion.

Updated on Nov. 24, 2026 in Business

Isometric editorial illustration of a concrete bridge deck under construction spanning a dry desert creek bed, with steel girders and new curbs in place.
Crews in Palm Springs are nearing completion of the $ replacement of the 1930 South Palm Canyon Bridge over Tahquitz Creek, with outside lanes finished Wednesday. AI Illustration. Upload story photo >

Crews reached the final stages of replacing the South Palm Canyon Bridge in Palm Springs, with work on the outside lanes completed Wednesday. One lane remains open in each direction, and all turns are open at East Sunny Dunes Road.

Why it matters

The original bridge, built in 1930, is structurally deficient and outdated, so the replacement addresses a safety and infrastructure need for drivers and cyclists in Palm Springs. The project is funded by a mix of local, state and federal sources.

The new 98-foot bridge replaces a structure built in 1930 and adds two lanes in each direction, a 14-foot concrete median and 8-foot sidewalks on each side. The project's total cost and whether the year's-end completion target will be met remain unconfirmed in the available information.

The details

The project reconstructs the bridge across Tahquitz Creek and the roadways at both ends, and includes a dedicated bicycle lane in each direction along with a public art installation in the center median. Crews began work in February 2025 and completed the outside lanes on Wednesday, with traffic maintained on one lane in each direction.

Timeline

  1. 1930: The original South Palm Canyon Bridge was built.

  2. February 2025: Construction on the replacement project began.

  3. Wednesday, November 19, 2026: Crews completed work on the outside lanes.

  4. Thursday and Friday, November 20-21, 2026: Crews are off-site for the Thanksgiving holiday.

  5. Year's end 2026: The project is expected to be completed.

Roadmap

The South Palm Canyon Bridge replacement follows a common pattern in which aging, structurally deficient bridges built decades ago are rebuilt using a mix of local, state and federal funding. The new design adds dedicated bicycle lanes and wider sidewalks, reflecting current standards for multimodal road infrastructure.

Drivers on South Palm Canyon Drive currently have one lane open in each direction, with all turns open at East Sunny Dunes Road. Once complete, the new bridge will provide dedicated bicycle lanes and wider sidewalks for pedestrians and cyclists.

The takeaway

Drivers and cyclists should expect lane restrictions to continue until the project is finished, and should check the project website for updates on the expected year's-end completion.

Further reading

Explore more local projects in the Construction section for Palm Springs.

More information

Find project updates on the South Palm Canyon Bridge project information page.