Metro Approves $300 Million D Line Budget Increase

The Los Angeles Metro Board Finance Committee advanced a 12% cost increase for D Line Section 2 ahead of a full board vote.

Updated on Nov. 23, 2026 in Construction

Metro Approves $300 Million D Line Budget Increase

Live Poll

Do you support continued public spending on local subway projects despite cost overruns?

The Metro Board Finance Committee approved a $300 million budget increase for D Line Section 2, raising its budget from $2.57 billion to $2.87 billion. The full Metro board is scheduled to vote on the increase at its December 3 meeting.

Why it matters

The increase brings Section 2 to 18% above its 2017 cost of $2.53 billion, adding to concerns about cost growth on the D Line extension. The cost rise is attributed to unforeseen factors that expanded construction scope and duration, along with compliance with restrictions imposed by Beverly Hills.

The Section 2 budget rose 12% to $2.87 billion, following a $134 million increase approved in 2023 and an overshoot of about 25% on Section 1, which opened in May. The full board vote on December 3 will determine whether the increase is finalized.

The players

Metro

The Los Angeles County Metropolitan Transportation Authority is the regional transit agency that builds and operates the county's rail and bus network.

Tim Lindholm

Tim Lindholm is a public official involved in the Metro budget discussion on the D Line Section 2 cost increase.

Patsy Ayala

Patsy Ayala is a public official involved in the Metro budget discussion on the D Line Section 2 cost increase.

The details

Unforeseen factors expanded the scope and duration of Section 2 construction, including tunneling around old oil wells under Beverly Hills High School. The Century City station was realigned to avoid old oil wells, and a Century City storm drain was moved to avoid ventilation impacts on a mall. Section 2 is more than 95% complete and Section 3 is about 90% complete.

Timeline

  1. 2017: Board approved the $2.53 billion Section 2 budget.

  2. Early 2018: Section 2 construction broke ground.

  3. 2023: Metro approved a $134 million Section 2 budget increase.

  4. May 2026: D Line Section 1 opened.

  5. December 3, 2026: Full Metro board votes on the cost increase.

Construction Context

The $300 million increase follows the $134 million raise Metro approved in 2023, extending a pattern of repeated budget growth on Section 2. The cumulative rise now places the project 18% above its 2017 cost, a trend that mirrors cost overruns on Section 1.

The vote on December 3 will determine whether the additional $300 million is approved for D Line Section 2. Riders can expect Section 2 and Section 3 to open in 2027, with Section 2 currently projected for around September.

The takeaway

Large public transit projects can face multi-year budget growth as unforeseen conditions expand scope, making board votes on cost increases a key checkpoint for tracking the D Line's final price.

What happens next

The full Metro board will vote on the cost increase at its December 3, 2026 meeting. D Line Section 2 is currently expected to open around September 2027, and Section 3 around December 2027.

Further reading

For more on local building projects, see Construction coverage in Los Angeles.

Source note: This article includes information reported by Streetsblog Los Angeles.