Beverly Hills Sidewalk Project Nears Completion

The village's Transportation Alternatives Program grant project is wrapping up, but costs have risen above the original estimate.

Updated on Nov. 16, 2026 in Lifestyle

Isometric editorial illustration of a plain concrete sidewalk beside a stacked stone retaining wall and an unfinished timber boardwalk, in muted slate, cream, and sage tones.
Beverly Hills village is wrapping up its Transportation Alternatives Program sidewalk connector, but costs have risen above the 2021 grant estimate, leaving an estimated $3.1 million in out-of-pocket costs for village taxpayers. AI Illustration. Upload story photo >

Live Poll

Do you trust your local government to manage public construction projects well?

The Village of Beverly Hills is wrapping up its Transportation Alternatives Program sidewalk connector project along 13 Mile Road, 14 Mile Road, Evergreen Road and Riverside Drive. Project costs have risen above the original 2021 grant estimate, with the village manager estimating village out-of-pocket costs at $3.1 million.

Why it matters

The gap between the 2021 grant application and current costs shifts the financial burden onto village taxpayers, since the fixed grant amount does not adjust for inflation. Residents in Beverly Hills will see the completed walkways and retaining walls, but the project illustrates how grant-funded infrastructure can exceed its original budget.

The TAP grant is a fixed $1.64 million that does not scale with inflation, while the original 2021 application estimated a $3.55 million total with $1.87 million in local funding. The village manager estimates out-of-pocket costs at $3.1 million, bringing the total project cost to $4.7 million, though the extraction does not detail how the remaining cost increase will be financed.

The players

Beverly Hills village government

The Village of Beverly Hills is a municipality in Oakland County, Michigan, which applied for and manages the TAP grant sidewalk connector project.

Michigan Department of Transportation (MDOT)

MDOT is the state agency that holds the TAP grant money and pays the contractor on the village's behalf.

Michigan State Historic Preservation Office

The State Historic Preservation Office is the Michigan agency that required an archaeological dig that contributed to project delays.

The details

All concrete sidewalks and stacked retaining walls are complete, with the remaining work including a wood boardwalk west of Lahser and a bridge east of Lahser. The project was delayed by right-of-way negotiations, an alternate route study, and an archaeological dig required by Michigan's State Historic Preservation Office, and grant funds are held by MDOT and paid to the contractor.

Timeline

  1. January 2021: First emails exploring sidewalk grants were sent.

  2. 2021: Village applied for the TAP grant based on a construction estimate.

  3. October 5, 2021: Agenda packet listed the $3.55 million total estimate.

  4. November 7, 2022: Village was notified it was in line for a $1.64 million grant.

  5. Spring 2027: Additional restoration work is scheduled to be completed.

Home Renovation Context

The Transportation Alternatives Program provides a fixed grant amount set at application, so projects that take years to reach construction can absorb cost increases that the grant does not cover. Beverly Hills' sidewalk connector shows how local governments must fill that gap with their own funds when inflation pushes costs above the original estimate.

Residents along 13 Mile Road, 14 Mile Road, Evergreen Road and Riverside Drive will gain continuous concrete sidewalks and retaining walls once the remaining boardwalk and bridge work is finished. Because village funds are covering the cost gap, the increase may be reflected in local budgets that affect other village services.

The takeaway

Grant-funded infrastructure projects can run over budget when the award is fixed and construction is delayed for years. Local governments should plan for cost increases between application and completion.

What happens next

Additional restoration work is scheduled to be completed in spring 2027.

Further reading

For more on local infrastructure upkeep, browse Home Renovation coverage for Beverly Hills.

Source note: This article includes information reported by West Bloomfield Beacon.

Live Poll

Do you trust your local government to manage public construction projects well?