Imperial District Approves Kane Spring Land Access

The easements clear a major hurdle for a 5,099-acre Salton Sea restoration project near Westmorland.

Updated on Nov. 25, 2026 in Environmental

Imperial District Approves Kane Spring Land Access

Live Poll

Do you trust local government to deliver environmental projects in your area?

The Imperial Irrigation District approved land access easements for the Kane Spring Project, a 5,099-acre restoration effort near Westmorland led by the state's Salton Sea Management Program. The Salton Sea Authority is also seeking temporary easements from property owners along the Bahia del Mar channels in Desert Shores.

Why it matters

The project is designed to curb dust emissions that are a persistent public health concern for surrounding communities, and to create habitat for endangered wildlife. The district's sign-off on land and water access clears a major hurdle toward moving the site into construction.

The restoration covers 5,099 acres, with its first phase anticipated to be funded through Proposition 4, though the source does not give a construction start date. Conceptual designs, environmental studies and site surveys are complete, but the funding timeline for later phases is not specified.

The players

Imperial Irrigation District

A public agency that supplies water and electricity to Imperial County in Southern California and controls the water access needed for the project.

Salton Sea Management Program

A California state program responsible for restoration efforts at the Salton Sea, the shrinking inland lake in Southern California.

The details

The Kane Spring Project was developed through a partnership of local, state and federal agencies and makes beneficial use of available water supplies. It is designed to establish ponds, channels, enhanced wetlands and native vegetation, and to stabilize exposed lakebed to curb dust emissions. The California Department of Water Resources issued a request for proposals in August to design and build the project.

Timeline

  1. August: California Department of Water Resources issued a request for proposals to design and build the project.

  2. November 17: Imperial Irrigation District approved land access easements for the Kane Spring Project.

Big Picture

The first phase of the Kane Spring Project is anticipated to be funded through Proposition 4, tying the restoration to the state's bond-funded approach to Salton Sea remediation. The project's progress depends on that funding moving forward alongside the district's land and water approvals.

Residents near the Salton Sea may see reduced dust exposure once the project is built, though the source gives no construction timeline. Property owners along the Bahia del Mar channels in Desert Shores are being asked to grant temporary easements so engineers can evaluate site conditions.

The takeaway

Restoring the Salton Sea depends on securing land and water access before construction can start, and this approval is a step toward that goal. Readers interested in the project's progress can watch for the funding and bid decisions that will determine when work begins.

Further reading

For related coverage, see Environmental news from California.

Source note: This article includes information reported by Imperial Valley Press Online.