ADOT Restricts I-19 Lanes Overnight in December

Overnight narrowing on Interstate 19 and left-turn limits on Irvington Road are part of a multi-year interchange widening project.

Updated on Nov. 26, 2026 in Industry

Isometric editorial illustration of two narrowed concrete highway lanes separated by orange-and-white barrels, running toward a desert mountain ridge beneath a plain overpass.
The Arizona Department of Transportation will narrow Interstate 19 in Tucson overnight from December 1 through December 11 and restrict left turns on Irvington Road through February 2027. AI Illustration. Upload story photo >

The Arizona Department of Transportation will impose overnight lane restrictions on Interstate 19 in Tucson from December 1 through December 11, 2026, from 9 p.m. to 5 a.m. Left turns on Irvington Road to Calle Santa Cruz will also be restricted through February 2027.

Why it matters

The restrictions affect drivers using one of Tucson's main north-south corridors and the Irvington Road interchange during overnight hours. The overnight work is part of a widening and improvement project that ADOT says is intended to meet traffic demands through 2045.

The $80 million total project cost includes $53.4 million in construction, and the overnight restrictions narrow both directions to one lane with a 16-foot vehicle width limit. Multiple delays have pushed the project back since it was first announced in December 2024, and the source does not say whether the current schedule will hold.

The players

Arizona Department of Transportation

The state agency responsible for the state highway system, including Interstate 19, and the lead authority on this widening project. ADOT plans, funds and manages highway construction and traffic restrictions across Arizona.

The details

Between Ajo Way and Valencia Road, both sides of I-19 will narrow to one lane each direction overnight, with the speed limit cut to 45 mph. The project widens Irvington Road from Calle Santa Cruz to 16th Avenue east of I-19, adds a new cloverleaf ramp for eastbound Irvington traffic onto northbound I-19, and adds a merge lane for northbound I-19.

Timeline

  1. December 2024: Project originally announced.

  2. December 1-11, 2026: Overnight I-19 lane restrictions occur.

  3. February 2027: Left-turn restriction on Irvington Road ends.

  4. Spring 2028: Nighttime Irvington restrictions end and the project is expected to finish.

  5. 2045: Improvements are expected to meet traffic demands.

Construction Pipeline

The I-19 and Irvington interchange widening is a Tucson project run by ADOT, the state agency that manages Arizona's highway network and its construction schedule. It is scheduled to finish in spring 2028 and is designed to handle traffic growth projected through 2045.

Drivers using I-19 between Ajo Way and Valencia Road should expect one-lane traffic and a 45 mph limit from 9 p.m. to 5 a.m. during the December 1-11 window, and vehicles wider than 16 feet may be affected. Anyone turning left from Irvington Road onto Calle Santa Cruz will need an alternate route until February 2027.

The takeaway

Overnight construction can be a planning factor for commuters on I-19 and Irvington Road in Tucson, so checking restriction hours before traveling in December can help avoid delays. The project's repeated delays also suggest that published completion dates may shift.

What happens next

Overnight lane restrictions on I-19 are scheduled for December 1-11, 2026, and the Irvington Road left-turn restriction runs through February 2027.

Further reading

For more on local road and highway work, see Construction coverage for the Tucson area.

More information

Details on the project are available through the I-19 and Irvington Road interchange project information page.

Source note: This article includes information reported by Green Valley News & Sun.