Tucson Closes Aviation Parkway for Bridge Work

The weekend closure lets crews remove sections of the 22nd Street bridge over the parkway as part of a $158 million rebuild.

Updated on Nov. 12, 2026 in Home Renovation

Wide view of an empty closed roadway beneath a concrete overpass, with steel bridge girders resting on the shoulder under a bright desert sky.
Tucson closed Aviation Parkway between Broadway and Golf Links Road from 8 p.m. Friday, Nov. 13, to 6 a.m. Monday, Nov. 16, so crews can remove bridge spans on the $158 million 22nd Street rebuild. AI Illustration. Upload story photo >

Barraza-Aviation Parkway will be closed between Broadway and Golf Links Road from 8 p.m. Friday, Nov. 13, until 6 a.m. Monday, Nov. 16. Crews are removing spans, overhangs, beams and piers from the 22nd Street bridge during the closure.

Why it matters

The current bridge, first built in 1966, cannot support buses, freight trucks or emergency vehicles, and the closure is needed to protect workers and the traveling public. The bridge has been closed to traffic since March, and the project is expected to take up to three years to complete.

The 22nd Street Bridge Revitalization Project carries a $158 million price tag and is expected to take up to three years. The original structure dates to 1966 and cannot carry buses, freight trucks or emergency vehicles.

The players

Union Pacific Railroad

Union Pacific is a major freight railroad operating across the western United States, and its tracks run beneath the 22nd Street bridge in Tucson.

The details

Crews are removing major bridge sections directly above Aviation Parkway, which requires closing the roadway between Broadway and Golf Links Road. The project will completely rebuild the 22nd Street bridge over Aviation Parkway and the Union Pacific railroad tracks.

Timeline

  1. 1966: The current 22nd Street bridge is first built.

  2. March 2026: The 22nd Street bridge is closed to traffic.

  3. 8 p.m. Friday, Nov. 13, 2026: Barraza-Aviation Parkway closure begins.

  4. 6 a.m. Monday, Nov. 16, 2026: Barraza-Aviation Parkway reopens.

Roadmap

Many urban overpasses built in the 1960s are now being replaced rather than repaired as their load capacity falls short of modern transit and freight needs. The 22nd Street project follows that pattern, with a full rebuild rather than a patch.

Drivers using Barraza-Aviation Parkway will need an alternate route between Broadway and Golf Links Road from 8 p.m. Friday, Nov. 13, until 6 a.m. Monday, Nov. 16. The 22nd Street bridge will remain closed to traffic during the three-year rebuild.

The takeaway

Plan alternate routes around Barraza-Aviation Parkway for the weekend of Nov. 13 to Nov. 16 and expect the wider bridge project to take up to three years.