Capstone Delays Pinto Valley Restart, Cuts Guidance
Additional maintenance at Arizona's Pinto Valley mine pushes primary crusher restart to mid-December and lowers the bottom of Capstone Copper's 2026 guidance.
Updated on Nov. 23, 2026 in Industry

Capstone Copper said additional maintenance at its Pinto Valley mine in Arizona has moved the restart of the primary crusher from early November to mid-December. The company also lowered the bottom end of its 2026 consolidated copper guidance from 200,000 to 195,000 tonnes.
Why it matters
The delay reduces expected copper output from a key Arizona operation, affecting supply from one of the state's mining sites. Temporary mobile crushers will support a partial concentrator restart in mid-November while the primary crusher remains offline.
Interim ore throughput with temporary mobile crushers reaches up to 40,000 tonnes per day, while the revised guidance range runs from 195,000 to 230,000 tonnes. The downtime is projected to cut 2026 output by roughly 5,000 tonnes, about 12% of 2025 production.
The players
Capstone Copper
Capstone Copper is a copper mining company that operates the Pinto Valley mine in Arizona along with other copper operations in the Americas.
The details
Pinto Valley primarily produces copper concentrate, with a small amount of SX-EW cathode. Mantoverde and Mantos Blancos, Capstone's other operations, were unaffected as of November 12, even as Chile's truckers' strike disrupted fuel supply and roadblocks were progressively lifted on November 13 after the main participating groups reached an agreement with the government.
Timeline
Early November: original expected date for the primary crusher restart at Pinto Valley.
Mid-November: partial concentrator restart planned using temporary mobile crushers.
November 12: Mantoverde and Mantos Blancos reported no production impact from the strike.
November 13: remaining roadblocks in Chile were progressively lifted.
Mid-December: revised date for the primary crusher restart.
Season Trajectory
Capstone's revised 2026 guidance, which lowers the bottom end from 200,000 to 195,000 tonnes while keeping the 230,000-tonne ceiling, narrows the company's expected output range rather than reversing its outlook. The adjustment places Pinto Valley's delayed restart within the broader production plan for the year.
Arizona residents who depend on the state's copper industry for jobs or local tax revenue may see the effects of reduced output at Pinto Valley through the coming months. The lower guidance floor signals that copper supply from this site will be somewhat tighter in 2026 than earlier forecasts suggested.
The takeaway
The Pinto Valley restart delay shows how a single site's maintenance can shift a company's full-year production range. Tracking the mid-December restart will show whether Capstone's revised guidance holds.
What happens next
The primary crusher at Pinto Valley is scheduled to restart in mid-December, with a partial concentrator restart planned for mid-November.
Further reading
Explore more Arizona manufacturing coverage for context on the state's industrial sector.
Source note: This article includes information reported by Metal.






