Fayetteville School Board Reviewed Construction Progress
The board examined status updates on four major district campus projects currently underway.
Updated on Sept. 25, 2026 in Secondary Education

Live Poll
Should your local school district prioritize large-scale construction projects to expand and modernize campus facilities?
Fayetteville officials have reviewed the development of four active school construction projects, including new campus facilities and parking improvements. These upgrades are central to the district's ongoing transition of its middle schools into junior high schools.
Why it matters
The district is investing in significant facility expansions to support its structural move toward a junior high model. These updates are intended to modernize academic and athletic spaces while also addressing logistical challenges like traffic congestion near school zones.
The Woodland Junior High campus is 65% complete at a cost of $99.6 million, while the Fayetteville High School parking garage has reached 75% completion. Additionally, the John L Colbert Middle School expansion is currently funded at nearly $24 million.
The players
Fayetteville School Board
This is the governing body responsible for overseeing the educational infrastructure and policy decisions for the local school district.
John L Colbert Middle School
This facility is currently undergoing a multi-million dollar expansion to convert its layout into a junior high school campus.
Woodland Junior High
This school site is the subject of a $99.6 million campus construction project that is currently more than halfway finished.
Fayetteville High School
This secondary educational institution is currently adding a parking garage to its facilities.
The details
The district is renovating the John L Colbert building to accommodate its new junior high status through expanded athletic and academic facilities. To improve area safety and access, construction is also underway on an eastern extension of Joyce Boulevard to reduce traffic at the Crossover Road intersection.
Timeline
New turf was installed at the Ramay field in September 2026.
The Woodland Junior High main building is expected to be topped out in October 2026.
The John L Colbert gymnasium renovation will conclude in November 2026.
Construction at John L Colbert Middle School is scheduled to wrap up in February 2027.
The Fayetteville High School parking garage project is expected to finish in April 2027.
Culture Shift
These construction projects follow a pattern set by the national shift toward junior high grade configurations. The expansion of these facilities reflects a broader move away from traditional middle school structures in favor of secondary models prioritized by modern districts.
Residents and parents should note that the John L Colbert gymnasium will remain closed for renovations until November. Additionally, traffic patterns near the Crossover Road intersection may fluctuate due to ongoing road extension construction.
The takeaway
These ongoing projects represent a multi-year effort to modernize the local school infrastructure to meet new grade-level requirements. Residents should plan for continued construction activity throughout the district until the spring of 2027.
Further reading
For more information on facility planning, visit the Secondary Education page.
Source note: This article includes information reported by Home Page.