Council Approves South Gay Street Bridge Replacement Deal

Auburn's City Council signed an agreement with the Alabama Department of Transportation to replace the aging bridge.

Updated on Nov. 11, 2026 in City Hall

Weathered concrete bridge with cracked deck edges over a creek, supported by aging timber piers and framed by red clay banks and hardwood trees under overcast daylight.
The Auburn City Council approved a preliminary agreement with the Alabama Department of Transportation and hired Barge Design Solutions for up to $457,103 to replace the 1965 South Gay Street bridge. AI Illustration. Upload story photo >

Live Poll

Do you trust Auburn's local government to spend tax dollars wisely on infrastructure?

The Auburn City Council approved a preliminary engineering and construction agreement with the Alabama Department of Transportation to replace the South Gay Street bridge. The council also hired Barge Design Solutions to survey the site and design the new bridge for up to $457,103.

Why it matters

The existing bridge is too weak for Auburn's fire trucks to cross, and its load rating prevents large vehicles from using it. Federal funding will cover about 80% of the expected project cost, with the city paying the rest along with land and utility costs.

The estimated $3.74 million project will be funded roughly 80% by federal money, leaving the city with about $747,774. Construction bids are not expected until December 2027, so final costs remain unknown.

The players

Auburn City Council

The elected governing body of Auburn, Alabama, responsible for approving municipal contracts and local infrastructure spending.

Alabama Department of Transportation

The state agency responsible for planning, building and maintaining Alabama's highways and bridges, including federally funded projects.

Barge Design Solutions

An engineering and design firm based in Hoover, Alabama, hired by Auburn to survey the site and design the replacement bridge.

The details

Auburn's council approved the ALDOT agreement and hired Barge Design Solutions on Nov. 3 for design and site survey work. The 1965 bridge rests on wooden piers more than 60 years old, and replacing only the top would not extend the structure's life.

Timeline

  1. 1965: The South Gay Street bridge was built with an expected lifespan of roughly 75 years.

  2. Nov. 3, 2026: The council approved the ALDOT agreement and hired Barge Design Solutions.

  3. Spring and summer 2027: The city plans to acquire needed land.

  4. Through much of 2027: Environmental review, soil testing and design work are planned.

  5. December 2027: The city plans to seek construction bids.

City Hall Context

The project follows the standard federal-aid local bridge program, in which ALDOT administers federal funds that cover most of the cost while the city pays for land, utilities and its share. It is part of Auburn's effort to address structurally deficient bridges that limit emergency vehicle access.

Fire trucks cannot currently cross the South Gay Street bridge, so the replacement is expected to restore emergency vehicle access once construction is complete. Residents should expect construction work and possible temporary traffic changes beginning more than a year from now.

The takeaway

Federal funding is covering most of the Auburn bridge replacement, so the city's largest near-term decisions involve land acquisition and design. Watch the 2027 bid process for the final price tag.

What happens next

The city plans to acquire needed land in spring and summer 2027, with environmental review and design work through much of 2027 and construction bids planned for December 2027.

Further reading

For more on local decisions like this, see City Hall coverage in Auburn.

Source note: This article includes information reported by Opelika Observer.

Live Poll

Do you trust Auburn's local government to spend tax dollars wisely on infrastructure?