Missile Warning Satellite Launch to Slip to May 2027
Space Systems Command moved the first launch of medium Earth orbit missile warning satellites from September 2026 to May 2027, citing component shortages.
Updated on Nov. 29, 2026 in Space

Space Systems Command plans to launch the first medium Earth orbit missile warning satellites in May 2027, eight months later than the previously planned September 2026 date. The Government Accountability Office attributed the delay to component shortages, including printed circuit boards.
Why it matters
The Resilient Missile Warning and Tracking Medium Earth Orbit program is a multibillion-dollar effort meant to strengthen U.S. detection of missile threats, so schedule slips affect when that capability reaches operational use. The delay also highlights how supply constraints for microelectronics can ripple through defense space programs.
The program's 22 satellites are split into a 12-satellite first epoch built by Millennium Space Systems and a 10-satellite second epoch for which Space Systems Command awarded BAE Systems about $1.2 billion in 2025. Officials have not yet fully resolved how component shortages will affect later batch schedules.
The players
Space Systems Command
The U.S. Space Force unit responsible for acquiring and developing military space systems, including the missile warning satellite program.
Government Accountability Office
The nonpartisan audit arm of Congress that evaluates federal programs and spending, and which documented the launch delay and its causes.
Millennium Space Systems
A satellite manufacturer, a subsidiary of Boeing, that builds the 12 Epoch 1 satellites for the program.
BAE Systems
A British defense and aerospace company awarded about $1.2 billion in 2025 to build the 10 Epoch 2 satellites.
The details
Program officials cited lead times and shortages for printed circuit boards and microelectronic parts, and said suppliers were producing components for the same vendor across multiple platforms. The program also switched to a different star tracker design after the previously selected supplier did not comply with 10 U.S.C. § 4864.
Timeline
November 27, 2023: Space Systems Command announced the critical design review for six Millennium Space Systems satellites was complete.
July 2025: Air & Space Forces Magazine reported the first launch had slipped to spring 2027.
October 2024: Space Systems Command awarded a $386 million contract for six more satellites.
September 8: Space Systems Command announced the Epoch 2 critical design review was complete for the first two orbital planes.
November 17: The Government Accountability Office issued a report documenting the launch slip and its cause.
Big Picture
The program's supplier change to satisfy 10 U.S.C. § 4864 shows how federal sourcing rules can force mid-program redesigns in defense space hardware. Similar microelectronics shortages have become a recurring constraint on U.S. military satellite schedules.
The delay means the new missile warning capability will not reach its first launch until May 2027 at the earliest. Taxpayers funding the $8.3 billion program should expect the schedule to remain under scrutiny as later batches proceed.
The takeaway
Supply shortages for basic electronic components can delay even well-funded national security satellites by months. Watching how the program handles its next batch award will show whether the schedule can be recovered.
What happens next
Industry responses on the program's next two batches of satellites are due December 1.
Further reading
For more on related developments, explore the Space section.
Source note: This article includes information reported by Tech Times.