Army Gets 180 of 12,000 Tank Rounds Due
Delivery delays on Northrop Grumman tank ammunition have stretched for years, and the Army has now awarded the company a further 10,000 rounds.
Updated on Nov. 27, 2026 in Military

Live Poll
Do you trust large defense contractors to deliver on government contracts?
As of late July 2026, the US Army has received 180 of the nearly 12,000 new tank rounds scheduled for delivery by that date from Northrop Grumman. The Army first accepted rounds in December 2024, more than three years after original delivery dates, and has contracted for nearly 22,000 rounds in total.
Why it matters
Delays and technical problems, including leaking primer material found in 2025 testing, have slowed the supply of tank ammunition the Army depends on. The March 2026 award of 10,000 more rounds shows the Army has chosen to keep working with the contractor rather than switch suppliers.
Army assessment reports rated the contractor's performance as marginal or unsatisfactory in five of seven reviews since 2018, and the Pentagon may not receive full value from nearly $224 million obligated under the contract. How the Army will recover the outstanding deliveries remains unresolved.
The players
Northrop Grumman
A major American defense contractor that manufactures aerospace and defense systems, including the tank ammunition at issue.
US Army
The land warfare branch of the US armed forces, which contracts for and receives the tank rounds.
The details
The contractor encountered technical and production problems that contributed to years of delays, and production involving the affected parts has been paused. Officials determined that switching contractors was impractical because the company had already made development progress, and changes to improve performance could add costs.
Timeline
December 2024: The Army first accepted new tank rounds, more than three years after original delivery dates.
2025: Leaking primer material was found during testing.
March 2026: The Army awarded Northrop Grumman a contract for 10,000 additional rounds.
July 2026: The cutoff for the 12,000-round delivery schedule passed with only 180 rounds delivered.
November 2026: An inspector general report was released.
Season Trajectory
Army assessment reports rated Northrop Grumman's performance as marginal or unsatisfactory in five of seven reviews since 2018, a pattern that the March 2026 award of 10,000 more rounds continues rather than breaks. The Army's decision to keep the contractor mirrors the reasoning that switching suppliers was impractical once development progress had been made.
The Army's continued reliance on Northrop Grumman means delays in tank ammunition supply may persist, affecting readiness timelines. Readers following defense spending can track future delivery reports and contract awards for updates on whether the remaining rounds arrive.
The takeaway
Large defense contracts can continue for years despite documented performance problems, because switching suppliers may be costlier than tolerating delays. Watching assessment reports and delivery counts offers a clearer picture of whether a contractor is improving than the contract award itself.
Further reading
Explore more Military coverage to see how defense procurement decisions like this one fit into broader Pentagon spending.
Source note: This article includes information reported by Business Insider.
Live Poll
Do you trust large defense contractors to deliver on government contracts?