Radiant Expands Nuclear Microreactor Manufacturing

Radiant Industries is investing $380 million across California and Tennessee to build its Kaleidos microreactors.

Updated on Nov. 24, 2026 in Manufacturing

Brushed steel cylindrical reactor vessel resting in a cradle inside a clean, bright concrete manufacturing bay under high daylight windows.
Radiant Industries will invest $380 million across California and Tennessee to scale production of its transportable Kaleidos microreactor, with deliveries targeted for 2028. AI Illustration. Upload story photo >

Live Poll

Should the U.S. expand nuclear microreactor production for military and commercial use?

Radiant Industries announced a $380 million dual-site manufacturing expansion in California and Tennessee to move its Kaleidos nuclear microreactor into commercial production. Initial customer deliveries are targeted for 2028.

Why it matters

The expansion moves a transportable nuclear reactor design toward commercial production, a step that could expand domestic capacity for advanced nuclear power. The investment also reflects growing federal and private demand for small, factory-built reactors.

Radiant is investing $380 million across two sites, including $100 million in El Segundo and $280 million in Oak Ridge, with the El Segundo facility adding about 200,000 square feet of manufacturing and R&D space. Regulatory approval from the Nuclear Regulatory Commission and the start of fueling operations in 2027 have not yet been confirmed.

The players

Radiant Industries

A nuclear technology company developing the Kaleidos transportable high-temperature gas-cooled microreactor, which uses helium coolant and TRISO fuel.

U.S. Army

The military branch that awarded Radiant up to $750 million under the Janus Program to deploy 15 Kaleidos units.

Nuclear Regulatory Commission

The independent federal agency that accepted Radiant's 10 CFR Part 70 license application for accelerated review.

Department of Energy

The federal department that approved Radiant's Documented Safety Analysis and is among its fuel supply partners.

The details

Radiant's first Kaleidos unit, built in El Segundo, is undergoing full-scale testing at the Idaho National Laboratory DOME facility. The Oak Ridge facility will let Radiant load fuel privately and ship factory-sealed, plug-in-ready reactors, and fuel supply agreements are secured with DOE, Centrus Energy, Urenco, and Standard Nuclear.

Timeline

  1. Late October: The Department of Energy approved Radiant's Documented Safety Analysis for its first unit.

  2. 2027: R-50 fueling operations are scheduled to begin in Oak Ridge.

  3. January 2027: The Nuclear Regulatory Commission's accelerated license review is targeted for completion.

  4. 2028: Initial customer deliveries of Kaleidos are targeted.

  5. 2030: All 15 Army Kaleidos units are expected to be deployed.

Market Landscape

The expansion positions Radiant to supply factory-built microreactors for military and commercial buyers as federal programs like the Army's Janus Program seek small, transportable power sources. Its Equinix agreement for 20 units adds a data-center customer to the military demand base.

For consumers, the expansion does not change near-term prices or product availability, since the Kaleidos units are not expected to reach customers until 2028. Its effect on household energy costs depends on whether these microreactors can be deployed at scale.

The takeaway

Small, factory-built reactors are moving from design to manufacturing, and the schedule for regulatory approval and customer deliveries will show whether that shift holds. Readers tracking energy infrastructure should watch the NRC review and the 2027 Oak Ridge fueling start.

What happens next

The Nuclear Regulatory Commission's license review is targeting completion in January 2027, and R-50 fueling operations in Oak Ridge are scheduled to begin in 2027.

Further reading

Explore more manufacturing coverage to see how other producers are scaling production.