ICE Buys 11 Warehouses for $1.07 Billion
A Government Accountability Office report finds the agency overpaid for properties and is paying for detention beds it does not use.
Updated on Nov. 22, 2026 in Immigration

Live Poll
Do you trust the federal government to spend tax dollars wisely?
Between January and March 2026, Immigration and Customs Enforcement purchased 11 industrial warehouses for about $1.07 billion to convert into migrant detention centers. A Government Accountability Office report released November 19, 2026 found that ICE paid at least 50% above assessed tax value for nine of the properties, and that the agency plans to sell seven of them.
Why it matters
The report questions whether ICE's rapid expansion of its detention system is being financed responsibly, as the agency pays for contracted beds that sit unused. Congress allocated $45 billion in July 2025 to maintain and expand the system, making oversight of how that money is spent a national concern.
The GAO recommended that ICE update its financial planning and assess full costs before additional purchases, and 55 of 87 invoice-review positions were vacant. The agency has not yet said how it will address these recommendations.
The players
Immigration and Customs Enforcement
The federal agency responsible for immigration enforcement and the detention of migrants, whose facility purchases are the subject of the report.
Government Accountability Office
The nonpartisan watchdog agency of Congress that audits federal spending and programs, and which produced the report on ICE's purchases.
Department of Homeland Security
The cabinet department that oversees ICE and its budget, and which shares responsibility for the agency's detention spending.
Dick Durbin
The U.S. senator from Illinois who made the GAO report public.
Donald Trump
The current President of the United States, whose administration intends to continue expanding the detention system.
The details
ICE signed contracts for 46,688 beds across 64 detention centers that require payment regardless of use, and it separately purchased four operating facilities for $2.2 billion. The GAO found that ICE failed to adjust its spending plans quickly enough as programs changed, and that the two Guantánamo Bay facilities, which cost about $111 million, housed fewer than 30 migrants per day on average.
Timeline
July 2025: Congress allocated $45 billion to maintain and expand ICE's detention system.
January to March 2026: ICE purchased 11 warehouses for about $1.07 billion.
July to August 2026: ICE purchased four operating detention centers for $2.2 billion.
November 19, 2026: The GAO report was released and made public by Sen. Dick Durbin.
Legal Context
The GAO's findings arrive after Congress's July 2025 allocation of $45 billion under the One Big Beautiful Bill Act to expand ICE's detention system. The report's warnings about planning and full-cost assessment bear directly on how that funding is being used.
Taxpayers are funding both the purchase of facilities and payments for beds that go unused, which the GAO says ICE has not adequately planned for. The planned sale of seven warehouses could further affect how much of the $1.07 billion is recovered.
The takeaway
Large federal spending on detention infrastructure depends on realistic planning and full-cost accounting, which the GAO found ICE lacked. Readers tracking immigration policy should watch whether the agency adopts those recommendations before making more purchases.