Navy Adds $72.6M to Lockheed F-35 Development Deal

The Pentagon modification expands a Lockheed Martin contract for F-35 Block 4 program support, as the upgrade remains delayed and over budget.

Updated on Nov. 21, 2026 in Transportation

Navy Adds $72.6M to Lockheed F-35 Development Deal

Live Poll

Should the U.S. keep spending more on delayed military aircraft upgrades?

The U.S. Navy added $72.6 million in scope to a Lockheed Martin F-35 development contract covering program management, software engineering, and cybersecurity support. The modification was awarded without competition and no money was obligated at the time of award.

Why it matters

The added scope arrives as Block 4 development upgrades are delayed and over budget, according to the Government Accountability Office. The modification is stated to accelerate F-35 Block 4 capabilities, with delays attributed to problems with Technology Refresh 3 hardware and software.

The modification raises the contract ceiling by $72.6 million on a base deal of about $1.44 billion, with no funds obligated at award. GAO found Block 4 at least $6 billion over budget, and the original 2026 target has slipped to 2029.

The players

Lockheed Martin

A major U.S. defense contractor and the prime manufacturer of the F-35 Lightning II fighter program.

U.S. Navy

The naval branch of the U.S. armed forces, whose Naval Air Systems Command awarded the modification.

Government Accountability Office

The independent audit and investigative agency of the U.S. Congress that reviewed the F-35 Block 4 program.

The details

The modification was awarded by Naval Air Systems Command at Patuxent River, Maryland, and adds scope to base contract N00019-23-C-0009, a 2023 undefinitized award. Most of the work is performed in Fort Worth, Texas (60%), with Nashua, New Hampshire (16%) and Baltimore (9%) also receiving shares.

Timeline

  1. April 2023: Technology Refresh 3 was originally due, and its problems have been the main source of Block 4 delay.

  2. July 2024: The Pentagon resumed accepting new F-35s after a pause of about a year.

  3. September 2025: A GAO report found Block 4 was at least $6 billion over budget and years behind schedule.

  4. March 2028: Modified work is expected to finish.

Market Landscape

The modification extends a sole-source development relationship with Lockheed Martin on the F-35 Block 4 upgrade, whose original 2026 target for 66 capabilities has slipped to 2029. The added scope, awarded without competition, reinforces Lockheed's position as the program's principal contractor while the upgrade remains behind schedule.

For taxpayers, the modification adds to the cost of a program GAO already found at least $6 billion over budget, with no funds obligated at award. The schedule slip means the upgraded F-35 capabilities that Block 4 promises are arriving years later than originally planned.

The takeaway

The added contract scope underscores that the F-35 Block 4 upgrade is still being funded and extended while its schedule and cost targets have already been missed. Readers following federal defense spending can track how such modifications change the program's total cost over the coming years.

What happens next

Work on the modified scope is expected to finish in March 2028, and GAO auditors expect Block 4 completion no earlier than 2031.

Further reading

For more on federal aviation and defense transport spending, see Transportation coverage on Wisevoter.

Source note: This article includes information reported by Defence Blog.