Data Center Construction Costs Rise 13% in U.S.

U.S. data center build costs climbed more than twice the global rate as power access and labor shortages slow project delivery.

Updated on Nov. 20, 2026 in Data Centers

Data Center Construction Costs Rise 13% in U.S.

Live Poll

Do you expect the prices of everyday technology to rise over the next year?

U.S. data center construction costs rose 13% year over year in 2026, more than twice the global rate and about three times the U.S. average annual gain over the past decade. The assessment covered more than 500 live or recently completed projects across 62 global markets.

Why it matters

Demand for artificial intelligence computing has outpaced the supply of powered land and the labor needed to build new facilities. Rising costs could affect the pace and price of data center expansion across the United States.

The assessment covered more than 500 live or recently completed projects across 62 global markets and surveyed 400 data center industry experts. Fifty-six percent of global respondents called power a major obstacle, and nearly one-third reported utility connection waits of more than two years.

The players

Turner & Townsend

Turner & Townsend is a global real estate and construction consultancy that publishes annual data center construction cost assessments.

The details

Contractors and subcontractors have built allowances for acceleration, overtime and labor attraction into their pricing, and charge higher fees for taking on the risk of delivering projects faster than usual. Just over one-quarter of survey respondents said their contractor capacity was sufficient to manage construction backlogs.

Timeline

  1. 2026: U.S. data center construction costs rose 13% year over year.

  2. Over the next year: construction cost increases are expected to moderate to between 6% and 10%.

Big Picture

The 13% U.S. increase is about three times the average annual gain recorded over the past decade in Turner & Townsend's annual data center construction cost assessments. That gap marks a sharp break from the slower cost growth that characterized the earlier years of the series.

Higher construction costs and longer utility waits could raise the price and delay the delivery of cloud and AI services that depend on new data center capacity. Households and businesses may see these pressures reflected in the pricing of digital services over time.

The takeaway

Power access and skilled labor, not just capital, now set the pace of data center expansion. Watching utility connection timelines is a useful signal for where capacity will come online.

Further reading

Explore more on Data Centers coverage for context on how power and labor limits are shaping buildout.

Source note: This article includes information reported by TokenPost.