Data Center Builders Face Steel and Tariff Squeeze
Skanska USA's Fall 2026 report warns of volatile data center construction costs as new Canadian material tariffs take effect.
Updated on Nov. 18, 2026 in Data Centers

Live Poll
Do you expect the prices of building materials to keep rising in your area?
Skanska USA's Fall 2026 Construction Market Trends Report warns that data center construction markets face growing volatility. New Section 338 tariffs on Canadian fabricated steel, plywood and lumber add to existing Section 232 duties.
Why it matters
Fabricated steel prices have risen above 40% this year, and lead times for some materials now exceed 60 weeks, raising costs and delays for projects across the country. Recent U.S.-Canada tariff actions have increased uncertainty around material costs for builders.
Fabricated steel prices are above 40% since the start of the year, with lead times over 60 weeks in some markets. Section 338 tariffs add 50% on Canadian fabricated steel and plywood and 45.2% on lumber.
The players
Skanska USA
Skanska USA is the American arm of the Swedish construction and development group Skanska, which builds commercial, infrastructure and data center projects.
President Donald Trump
Donald Trump is the current President of the United States, whose administration introduced the Section 232 tariffs that the new Section 338 duties add to.
The details
Section 338 tariffs were imposed on fabricated steel, plywood and lumber from Canada, applied in addition to Section 232 tariffs introduced in 2025. Skanska USA says projects that secure power, labor and long-lead materials early are better positioned to hold schedules and budgets, while U.S. domestic steel mills are nearing capacity.
Timeline
2025: Section 232 tariffs introduced by President Trump.
Start of 2026: Fabricated steel pricing rose above 40%.
September 2026: Revisions to Section 338 tariff coverage.
Fall 2026: Skanska USA releases its Construction Market Trends Report.
2027: Major data center projects expected to move from planning to construction.
Big Picture
The new Section 338 tariffs layer onto the Section 232 duties first introduced in 2025, compounding cost pressure on the steel and lumber that data center builders depend on. The result is a second trade-policy shock arriving while domestic mills are already near capacity.
Developers and contractors may face higher and less predictable material costs, which can push back project timelines and budgets for new facilities. Early procurement of power, labor and long-lead materials is the main lever the report identifies for holding schedules.
The takeaway
Projects that lock in power, labor and long-lead materials early are better positioned to absorb tariff-driven cost swings. Watching tariff revisions closely may matter as much as tracking data center demand itself.
What happens next
Major data center projects are expected to move from planning into construction in 2027, when the market volatility Skanska describes could become most visible.
Further reading
For more on the infrastructure behind this build-out, see Data Centers coverage.