Intersect Reserves 1.5GW of Heron Transformers
Alphabet-owned Intersect secures transformer capacity from Heron Power, with deliveries slated to begin in 2028.
Updated on Nov. 17, 2026 in Data Centers

Live Poll
Do you expect your household electricity bill to rise over the next few years?
Intersect, a clean energy and data center developer owned by Alphabet, has reserved 1.5GW of Heron Link medium-voltage transformers from Heron Power. Heron Power will begin delivering the capacity to Intersect in 2028.
Why it matters
The agreement secures power infrastructure for data center growth as demand for electricity from AI and cloud computing rises across the United States. Intersect said the platform should accelerate its speed to power by improving energy delivery efficiency.
The reserved capacity equals 1.5GW of Heron Link transformers, each rated at 5MW and built on wide-bandgap semiconductors, with Heron Factory One designed to produce up to 10,000 units annually. Deliveries are expected to commence in 2028, and the units' performance in field deployment has not yet been reported.
The players
Intersect
Intersect is a clean energy and data center developer owned by Alphabet that operates solar, storage and data center assets, including projects with Google.
Heron Power
Heron Power is a US manufacturer of solid-state medium-voltage transformers, founded in 2024 by former Tesla senior executive Drew Baglino.
The details
Heron Power, a US manufacturer of solid-state medium-voltage transformers founded in 2024 by former Tesla senior executive Drew Baglino, will manufacture the units at Heron Factory One in Morgan Hill, California. Intersect and Heron have had a technical and commercial relationship for more than 18 months, and last month Heron signed a deal with Vantage to deploy more than 1GW of transformers.
Timeline
Alphabet announced its acquisition of Intersect last December.
Alphabet closed the Intersect acquisition in March.
Intersect and Google began construction at the Meitner Energy Center in June.
Mass production at Heron Factory One is expected to start in late 2027.
Deliveries to Intersect are expected to commence in 2028.
The Tech Race
The deal positions Heron's solid-state Heron Link against conventional oil-filled transformers as data center developers compete for scarce grid equipment. Heron's separate agreement with Vantage for more than 1GW suggests the solid-state design is gaining traction among multiple large operators.
Faster, more efficient power delivery to data centers can influence the cost and speed of cloud and AI services that businesses and consumers rely on. The deal signals that grid equipment constraints remain a key factor in how quickly new computing capacity can come online.
The takeaway
Power equipment, not just chips, is becoming a bottleneck for computing growth, and manufacturers securing long-term capacity agreements are gaining leverage. Readers tracking data center expansion should watch whether grid components like transformers keep pace with planned builds.
What happens next
Heron Factory One is expected to begin mass production in late 2027, and deliveries to Intersect are scheduled to begin in 2028.
Further reading
For more on how power infrastructure is shaping the buildout, explore Data Centers coverage.
Source note: This article includes information reported by Datacenterdynamics.