The Energy Department on Tuesday backed a conditional $2.8 billion loan to Grid United to build the 100-mile Wyoming Intertie linking the eastern and western U.S. power grids. AI Illustration. Upload story photo >

Live Poll

Do you expect your electricity bills to go down over the next few years?

The Department of Energy's Office of Energy Dominance Financing announced a conditional loan commitment of up to $2.8 billion to independent transmission company Grid United on Tuesday. The funds will support the Wyoming Intertie, a transmission line of more than 100 miles that will use high-voltage direct current technology for the first time in the United States.

Why it matters

The project is designed to connect the eastern and western power grids and expand delivery capacity, with the loan framed as part of the administration's effort to strengthen the grid and lower electricity prices. Affordability was one of the top voter issues in the Nov. 3 midterm elections, and electricity prices rose 0.9% in October from the previous month.

The up-to-$2.8 billion conditional loan covers part of a project costing just under $4 billion, with a delivery capacity of up to 1.8 gigawatts over more than 100 miles. Whether the loan is finalized and how the project's projected cost savings will materialize remain unresolved.

The players

Grid United

Grid United is an independent transmission company developing the Wyoming Intertie project and serving as the recipient of the conditional federal loan.

U.S. Department of Energy

The U.S. Department of Energy is the federal agency whose Office of Energy Dominance Financing issued the conditional loan commitment for the transmission line.

The details

The Wyoming Intertie will use high-voltage direct current voltage source converter technology for the first time in the United States. The project is expected to have a 30-year lifespan, and the administration hopes it will be complete by 2033.

Timeline

  1. Nov. 3, 2026: Midterm elections where affordability was a top voter issue.

  2. September 2026: The Department of Energy unveiled approximately $5 billion across 31 projects.

  3. Nov. 17, 2026: The conditional loan commitment was announced on Tuesday.

  4. 2033: The administration hopes the Wyoming Intertie will be complete.

Roadmap

The conditional loan follows the Department of Energy's September round of roughly $5 billion across 31 transmission projects in 26 states. It extends that federal push to a single long-distance, high-voltage direct current line that the department frames as a way to connect the eastern and western grids.

The loan itself does not change household bills, but the administration argues the transmission line could deliver up to $39 billion in electricity cost savings for families and businesses across the WECC and SPP regions. Those savings are a projection, and any effect on monthly utility costs would depend on how the project is built and operated.

The takeaway

Large transmission projects can take years to finish, so near-term electricity prices are shaped more by current supply and demand than by lines still in planning. Readers tracking utility costs should watch whether the conditional loan is finalized and whether the 2033 completion target holds.

Further reading

Explore more utilities coverage for the grid and power-market context behind this loan.

Live Poll

Do you expect your electricity bills to go down over the next few years?