Border Wall Nears 2029 Finish Amid Texas Pushback
About 619 miles of primary wall remain to be built as construction faces lawsuits and landowner resistance in West Texas.
Updated on Nov. 17, 2026 in Immigration

Live Poll
Should the federal government finish the full border wall even over local objections?
As of November 10, 2026, Customs and Border Protection data showed about 619 miles of primary border wall still to be built, with much of the remaining mileage in Texas. The Trump administration's projected completion date now stands at late 2029, with the pace of construction rising in recent months.
Why it matters
Resistance from private landowners and Texas officials has pushed federal authorities toward individual eminent domain cases and has produced more than a half dozen lawsuits in West Texas. The outcome will shape how and where the federal government can complete physical barriers along the southern border in the United States.
Customs and Border Protection data shows 619 miles of primary wall remain, with weekly construction pace rising from 2.6 miles to 3.9 miles between mid-June and early November 2026. The state of Texas owns 31 linear miles of land along the border, and it is unresolved how the pending lawsuits will affect the remaining mileage.
The players
Customs and Border Protection
The federal agency responsible for border security and the primary agency overseeing construction of the border wall.
Markwayne Mullin
The U.S. Homeland Security Secretary who earlier planned for a physical wall from the Pacific to the Gulf of America by late 2027.
Rodney Scott
The CBP Commissioner who extended the wall completion deadline to the end of 2027.
The details
The federal government is building the wall through contracts with border wall contractors and is filing individual eminent domain cases for each private plot needed, including a case against a church in New Mexico. The Texas General Land Office sent a cease-and-desist letter to CBP and a contractor in July 2026 over unauthorized construction, and the Big Bend sector has become a focal point of resistance.
Timeline
July 2026: Texas General Land Office sends cease-and-desist letter to CBP and a border wall contractor.
Mid-June 2026: Wall construction pace increases to 3.9 miles per week.
November 3, 2026: Midterm elections remove several of Trump's biggest Texas allies from office.
November 10, 2026: CBP data shows 619 miles of primary wall remaining.
End of 2027: CBP extends its deadline for completing the wall.
Political Context
The federal government's reliance on individual eminent domain cases for border barrier land echoes the land acquisition battles that have accompanied border wall construction since the first wall projects. Texas officials and landowners now oppose physical barriers in West Texas and the Big Bend area, creating legal and political friction that is shaping the pace of the current build.
Landowners along the border, particularly in West Texas, may face federal eminent domain filings for the land needed for the wall. Residents and businesses in border regions should expect continued construction activity and ongoing lawsuits as the projected completion date of late 2029 approaches.
The takeaway
Track how the pending lawsuits and eminent domain cases resolve, since they will determine whether construction stays on the projected timeline. Landowners facing federal filings can consult the court dockets for their own cases to understand their options.
Further reading
Explore more coverage in the Immigration section for context on border policy debates.
Source note: This article includes information reported by Axios.