Talamore Receives Draft Coffee Gold Mining License
Talamore Mining Corp. has received a draft Quartz Mining License for its 100%-owned Coffee Gold Project in Yukon.
Updated on Nov. 24, 2026 in Public Companies

Live Poll
Do you support new large gold mines in northern Canada?
Talamore Mining Corp. received a draft Quartz Mining License for the Coffee Gold Project from the Yukon Government's Department of Energy, Mines and Resources, announced November 24, 2026. The company has also substantially advanced construction of the Northern Access Route to support winter transportation of materials to the site.
Why it matters
The draft license follows a technical, environmental, engineering and regulatory review, while Yukon Government consultation with potentially affected First Nations is still underway. For Yukon, the project is expected to be a significant contributor to the territory's economy, with the company projecting about $80 million in spending in 2026.
The Coffee Gold Project hosts 3.0 million ounces of Measured and Indicated gold resources and 0.8 million ounces of Inferred resources, with Talamore projecting about $80 million in 2026 spending in the Yukon economy, 70% of it directed to First Nations businesses. The final Water Use Licence timeline and the outcome of the public comment process remain unresolved.
The players
Talamore Mining Corp.
A Vancouver, British Columbia-based company with 100%-owned gold project in Yukon and copper and gold assets in Chile and Mexico.
The details
The draft Quartz Mining License was issued after a technical, environmental, engineering and regulatory review, and Yukon Government consultation with potentially affected First Nations is underway. The Northern Access Route is being built to carry construction materials, equipment and supplies during the upcoming winter season, and Talamore will begin using it once as-built reports are submitted and the Yukon Government confirms construction is complete.
Timeline
September 15: The public comment period for the Water Use Licence closed.
November 24, 2026: Talamore announced receipt of the draft Quartz Mining License.
Early December: The company expects to begin filing responses to Water Use Licence comments.
Upcoming winter season: Winter transportation of materials to the project is planned.
2027: Mine construction is planned to start.
Market Landscape
The draft license places Talamore's Coffee project within Yukon's Quartz Mining Act licensing sequence, which requires a draft license before the final license and a separate Water Use Licence. The step positions the company's Yukon gold resource alongside its copper and gold holdings in Chile and Mexico as it advances toward construction.
For Yukon residents, the project is expected to bring about $80 million in 2026 spending into the territory's economy, with 70% directed to First Nations businesses. Local hiring and business opportunities will depend on the final license and construction timeline, which are not yet set.
The takeaway
A draft license is an important milestone, but the Water Use Licence and final Quartz Mining License still determine when the Coffee project can move toward construction. Readers tracking Yukon's resource sector should watch the Water Board's review and the consultation with First Nations.
What happens next
Talamore expects to begin filing responses to Water Use Licence comments in early December, and mine construction is planned to start in 2027.
Further reading
For more on the companies behind regional projects, see Public Companies coverage.
Source note: This article includes information reported by Stratford Beacon Herald.
Live Poll
Do you support new large gold mines in northern Canada?