Construction Materials Left Outside Rot in Nunavut
Housing supplies stored unattended for years in Nunavut communities are being damaged, and a fire in Naujaat has delayed eight public housing units.
Updated on Nov. 22, 2026 in Government

Live Poll
Do you think public housing projects in your area are getting built on time?
Crates of construction materials for public housing burned in a fire in Naujaat, Nunavut, in August, after sitting unattended outside for two years, delaying construction of eight units. Similar materials bound for Pangnirtung have been left near the harbour since 2024.
Why it matters
Materials are shipped during the short Arctic shipping season and stored outside until construction can begin, and some may be damaged or moldy by the time buildings go up. The problem affects housing supply for communities across Nunavut.
The reported figures are eight delayed housing units in Naujaat and two years of outdoor storage before the fire, with materials in Pangnirtung stored since 2024. How much of the material is damaged and when construction will resume remain unknown.
The players
NCC Development
NCC Development is the company tasked with building public housing for the Government of Nunavut, and its materials were burned in Naujaat.
The details
NCC Development, the company tasked with building public housing for the Government of Nunavut, ships as many materials as possible to communities in advance of construction. Construction cannot start until other preparatory steps are completed, so materials are left outside in the interim, where they are left to rot.
Timeline
2024: Materials for Pangnirtung housing were placed near the harbour.
August 2026: Crates of construction materials burned in a fire in Naujaat.
Government
Because the Arctic shipping season is short, materials for public housing in Nunavut must arrive early and wait outdoors, which is why the Naujaat and Pangnirtung stockpiles have sat for up to two years. The pattern shows how seasonal logistics shape the pace of territorial housing construction.
For residents waiting on public housing in Nunavut, delayed construction means longer waits for units. Materials stored outside may need to be replaced or repaired, which could affect project timelines and costs for the territorial government.
The takeaway
Housing delays in Nunavut are tied not only to funding but to the logistics of a short shipping season, so timely delivery and storage planning matter for getting homes built. Residents should watch for updates on rebuilt schedules for the affected communities.
Further reading
For more on how the territory manages public programs, see the Government section.
Source note: This article includes information reported by CBC News.