Alberta Approves 1,494-MW Plant for Calgary Data Centre
The Alberta Utilities Commission has cleared a power plant to fuel a proposed hyperscale data centre near Calgary despite community opposition.
Updated on Nov. 18, 2026 in Data Centers

Live Poll
Should Alberta keep approving new data centre power plants near your community?
The Alberta Utilities Commission approved a 1,494-megawatt power plant that will supply a proposed hyperscale data centre near Calgary. The plant is being developed by a subsidiary of Beacon Data Centers, and over 20 nearby landowners raised concerns during proceedings.
Why it matters
The decision shows the AUC can override a municipality on power plant approvals, which matters for Albertans living near large industrial sites. It also reflects provincial rules requiring data centre developers to build their own power supply after restrictions on grid connections.
The approved Indus plant has a capacity of 1,494 megawatts, while the two Sturgeon County plants total 2,766 megawatts. Whether the Indus data centre will secure a tenant has not been determined.
The players
Alberta Utilities Commission
The Alberta Utilities Commission is the provincial regulator responsible for approving utility and power infrastructure projects in Alberta.
Beacon Data Centers
Beacon Data Centers is a data centre developer founded in 2023 by New York-based venture capital firm Nadia Partners.
Rocky View County
Rocky View County is the municipality northeast of Calgary where the Indus power plant is located.
Meta
Meta is the technology company behind a $13-billion data centre planned for Sturgeon County.
The details
The commission's approval overrules Rocky View County, though the municipality may still apply conditions that do not conflict with the AUC's requirements. Plans for the site changed after the province restricted grid connections for data centres and directed developers to build their own power supply.
Timeline
July 2025: Municipality approved a general site plan without a power plant.
August and September 2026: Landowners raised concerns during AUC proceedings.
November 17, 2026: AUC approved the Indus power plant.
November 18, 2026: Province announced new guidelines on data centres in Edmonton.
Before the end of 2026: Construction on the power plant is expected to begin.
Big Picture
The approval follows Alberta's rule requiring data centre developers to generate their own power after the province restricted grid connections for these facilities. It shows how that policy is now producing large dedicated power plants near Calgary and Sturgeon County.
Residents living near the Indus site may see construction and transmission activity over the coming years. Nearby landowners have been offered sums to sell their land, which affects those deciding whether to stay.
The takeaway
Large power projects tied to data centres are now being approved in Alberta, and the regulator's decisions can override local planning. Residents near these sites should watch for conditions the municipality may still set.
What happens next
Construction on the Indus power plant is expected to begin before the end of 2026, and the plant is forecast to come online in the final quarter of 2027.
Further reading
For more on how the province is shaping this sector, see our Data Centers coverage.
Source note: This article includes information reported by The Globe and Mail.