FireFly Extends High-Grade Copper-Gold at Green Bay
New drilling at the Green Bay Project in Canada extends mineralisation beyond the current resource and may strengthen the economics of a feasibility study underway.
Updated on Nov. 9, 2026 in Economic Indicators

FireFly Metals reported further high-grade copper-gold drilling results from its Green Bay Project in Canada, including 16.4 metres at 9.2% copper equivalent. The drilling extends mineralisation outside the current resource.
Why it matters
Converting inferred material into higher-confidence resource categories is critical because only measured and indicated resources can be used in the mine plan and economic analysis. The results may strengthen the economics of the definitive feasibility study now underway.
The drilling results are assay intercepts rather than resource figures, with 16.4 metres at 9.2% copper equivalent and 6.9 metres at 10.0% copper equivalent reported outside the current Core Zone resource of 18.1 million tonnes at 4.3% copper equivalent. Whether the 7.0 million tonnes of inferred material and the new extensions will be upgraded to higher-confidence categories remains unresolved until the updated estimate.
The players
FireFly Metals
FireFly Metals is the company developing the Green Bay Project and reporting the drilling results.
The details
Drilling targeted lateral extensions outside the current mineral resource, with six underground drill rigs active at the Ming Mine split between resource extension and infill work. Selective clearing, camp expansion and upgrades to electrical and wastewater systems are underway at Green Bay.
Timeline
September 30, 2026: FireFly held approximately A$349.7 million in cash and liquid investments.
End of 2026: The company plans to order selected long-lead items.
March quarter of 2027: An updated mineral resource estimate and a maiden ore reserve are targeted.
July 2027: Formal construction is targeted, subject to a board investment decision.
Market Landscape
The Green Bay Project sits within Canada's broader critical minerals push to build domestic copper supply. Its progress from exploration toward a feasibility study and construction target places it among the country's advancing copper development projects.
For Canadian households, progress on domestic copper projects can influence long-term supply for electrical and construction uses. The project's timeline depends on conversion of resources and a board investment decision, so near-term effects on everyday costs are not established.
The takeaway
Resource conversion from inferred to measured categories will determine whether the Green Bay Project advances to construction. Readers should watch the updated estimate due in the March quarter of 2027.
What happens next
The updated mineral resource estimate is scheduled for the March quarter of 2027, followed by formal construction targeted for around July 2027 subject to a board investment decision.
Further reading
Explore more on Economic Indicators to see how resource development fits into national economic trends.
Source note: This article includes information reported by Proactiveinvestors NA.






