Greens and Independents Seek Longer Sittings for Stadium Scrutiny
Thirteen MPs ask Premier Jeremy Rockliff and Labor leader Josh Willie to extend parliament's sitting days into December over the Macquarie Point stadium costs.
Updated on Nov. 16, 2026 in Legislative Policy

Live Poll
Do you trust your state government to be open about big public project costs?
Thirteen Greens and independent MPs have asked Premier Jeremy Rockliff and Labor leader Josh Willie to extend parliament's sitting days into December. The request centres on scrutiny of the final costings for the Macquarie Point stadium, due to go to cabinet in the week of 30 November.
Why it matters
The total stadium budget is $1.13 billion, with the state government contribution capped at $875 million, and the MPs have raised concern that sharp construction cost rises linked to international conflict could strain that cap. Labor has warned that extending sitting days could send Tasmanians to another early election.
The total stadium budget stands at $1.13 billion, while the state government contribution is capped at $875 million. Cabinet must approve the tender price if it exceeds $1.13 billion, and whether final costings stay within the cap remains unresolved.
The players
Jeremy Rockliff
Jeremy Rockliff is the Premier of Tasmania, leading the Liberal government responsible for the state's stadium project.
Josh Willie
Josh Willie is the leader of the Tasmanian Labor Party in parliament.
The details
Thirteen Greens and independent MPs from both houses signed letters to Premier Jeremy Rockliff and Labor leader Josh Willie asking for support to extend sittings into December. The letters cite sharp construction cost increases from international conflict and seek scrutiny before the construction contract with preferred builder BESIX Watpac is signed.
Timeline
Week of 30 November 2026: final stadium costings due to go to cabinet.
Before Christmas 2026: construction contract with BESIX Watpac expected to be signed.
December 2026: proposed extended parliamentary sitting days.
Political Context
Both houses of parliament already passed motions this year calling for updated stadium costs, and Labor supported both. The current letters push that earlier demand further by asking for extended sittings to examine the final figures before the contract is signed.
The outcome determines whether the $875 million state contribution holds or whether additional costs fall to taxpayers. Sitting days into December would also affect when MPs can scrutinise the final figures before the contract is signed.
The takeaway
Watch whether the final costings fit within the $875 million cap before cabinet decides. The gap between the $1.13 billion total and the state contribution will shape how much scrutiny follows.
What happens next
Final stadium costings are due to go to cabinet in the week of 30 November 2026, and the construction contract with BESIX Watpac is expected to be signed before Christmas.
Further reading
For more on how these decisions are made, see Legislative Policy coverage across Tasmania.
Source note: This article includes information reported by Pulse Tasmania.