Harmony Gold's Eva Copper Project Reaches 15%
Harmony Gold says construction of its Queensland copper project is about 15% complete, with first production targeted for late 2028.
Updated on Nov. 26, 2026 in Industry

Harmony Gold reported on 9 November 2026 that construction of its Eva copper project in Queensland, Australia, was approximately 15% complete. The project was approved in November 2025 and first production remains targeted for late 2028, subject to further federal environmental approvals.
Why it matters
The Eva project would add a significant new source of copper alongside Harmony's existing CSA mine in Australia. Its progress offers a benchmark for Harmony's wider copper ambitions, including the Wafi-Golpu joint venture in Papua New Guinea, which has no confirmed start-up schedule.
The figures come from Harmony Gold's own construction update, which puts Eva at about 15% complete against an estimated capital cost of US$1.55-1.75 billion. The company has not resolved the remaining federal approvals or confirmed a Wafi-Golpu start-up schedule.
The players
Harmony Gold
Harmony Gold is a South African-founded gold and copper mining company listed on the New York and Johannesburg stock exchanges, with operations in Australia and Papua New Guinea.
Newmont
Newmont is one of the world's largest gold mining companies and is Harmony's partner in the Wafi-Golpu joint venture in Papua New Guinea.
The details
Eva is being built in Queensland and will produce copper-in-concentrate alongside gold. Combined with the CSA mine, annual copper output is expected to approach 100,000 tonnes once Eva is running and CSA reaches its optimisation target.
Timeline
November 2025: Eva project approved.
9 November 2026: Harmony reports construction about 15% complete.
Late 2028: First production targeted at Eva, subject to approvals.
2028-2029: Wafi-Golpu start-up window, with no schedule confirmed.
Market Landscape
Eva extends Harmony's copper footprint beyond its existing CSA mine in New South Wales, and combined output is projected to approach 100,000 tonnes a year once both are at target. That positions Harmony to compete more directly for copper supply as miners race to expand production.
For households, a larger copper supply can influence the cost of wiring, electronics and construction materials over time. The project's first production is still years away, so no near-term price change follows directly from this update.
The takeaway
Mining project timelines depend heavily on approvals, so a 15% construction milestone is an early signal rather than a guarantee of 2028 output. Watch for federal approval decisions as the next real test for Eva.
What happens next
Harmony Gold's Eva project still needs further federal environmental approvals before first production, which is targeted for late 2028.
Further reading
Explore more Industry — General coverage on how mining projects like Eva are progressing across Queensland.
Source note: This article includes information reported by Metal.