Greenvale Energy Limited began a new phase of field exploration this week at its Henbury Uranium Project south of Alice Springs, sampling 21 priority targets. AI Illustration. Upload story photo >

Greenvale Energy Limited has commenced a new phase of field exploration at its Henbury Uranium Project, located south of Alice Springs in the Northern Territory. The program focuses on geological mapping and systematic sampling of 21 priority uranium targets identified by 2025 geophysical and geological work.

Why it matters

The Henbury project sits within the Amadeus Basin, which hosts the Angela Deposit, and the new program advances early-stage assessment of the targets in Exploration Licences 33637 and 33638. Northern Territory residents with an interest in the state's uranium resource base can track whether the targets progress toward further evaluation.

Handheld RS-125 spectrometer readings returned up to 37ppm equivalent uranium from outcropping sandstone at Target 1, among 21 priority targets identified in 2025. Independent laboratory analysis of submitted samples has not yet been completed, so the grade of the targets remains unconfirmed.

The players

Greenvale Energy Limited

Greenvale Energy Limited is an ASX-listed, uranium-focussed exploration company that also owns the Oasis Uranium Project in Queensland.

Alex Cheeseman

Alex Cheeseman is the Managing Director of Greenvale Energy Limited, who described the Henbury project as an early-stage opportunity.

The details

Greenvale Energy Limited's current field program concentrates on geological mapping and systematic sampling of the identified targets, with samples to be submitted for independent laboratory analysis. The present program is expected to take between 10 and 15 days to complete.

Timeline

  1. 2025: Geophysical and geological programs identified 21 priority uranium targets.

  2. 22 November 2026: Greenvale announced the commencement of the new Henbury field exploration phase.

  3. Q1 2027: Laboratory results from the Henbury program are anticipated.

  4. After the 2027 wet season: Initial fieldwork at the Elkedra Uranium Project is planned, following its postponement due to heavy rainfall and localised flooding.

Big Picture

The Henbury program is being carried out in the Amadeus Basin, the same basin that contains the Angela Deposit, placing the early-stage exploration within a known uranium-bearing geological setting. Whether the 21 priority targets can match that precedent will depend on the laboratory results expected in the first quarter of 2027.

For Northern Territory residents, the Henbury program is an early exploration step that could eventually inform future uranium supply in the region, but it does not yet change any practical outcome. Any commercial development would depend on whether the laboratory results from the 21 targets justify further work.

The takeaway

Early-stage exploration results like these are preliminary, so the key indicator to watch is the laboratory assay data expected in early 2027. Readers should treat the 37ppm reading as a field screening value rather than a confirmed resource grade.

What happens next

Laboratory results from the Henbury program are expected in the first quarter of 2027, and fieldwork at the Elkedra Uranium Project is planned after the 2027 wet season.