Tamboran Completes Three Beetaloo Basin Wells

Drilling on the SS1 pad in Australia's Beetaloo Basin has finished, with stimulation planned for later this year.

Updated on Nov. 16, 2026 in Oil and Gas

Bold flat-color editorial illustration of a lone steel drilling derrick and wellheads on a red earth pad under open outback sky.
Tamboran Resources and Daly Waters Energy finished drilling three horizontal wells at the SS1 pad in Australia's Beetaloo Basin, with stimulation planned later this year. AI Illustration. Upload story photo >

Tamboran Resources and Daly Waters Energy completed drilling three horizontal wells on the SS1 pad in the Beetaloo Basin. The SS1-6H and SS1-4H wells were drilled and cemented to total depth in 32 and 24 days, with usable laterals of 9,434 ft and 9,635 ft.

Why it matters

The completed wells move the Beetaloo Joint Venture closer to production in the Northern Territory's gas-prospective basin. The programme shows the drilling sequence needed before stimulation and tie-back to existing infrastructure.

The SS1-6H and SS1-4H wells were drilled in 32 and 24 days respectively, with usable laterals of 9,434 ft and 9,635 ft. Results from stimulation, planned for Q4 2026, have not yet been reported.

The players

Tamboran Resources

Tamboran Resources is an Australian energy company focused on developing unconventional gas resources in the Beetaloo Basin, and holds a 25% interest in EP 161.

Daly Waters Energy

Daly Waters Energy is a company participating with Tamboran in drilling and developing wells in the Beetaloo Basin.

Santos

Santos is a major Australian oil and gas producer that operates the EP 161 permit, where the JS-DW1 well was drilled.

The details

The SS1-6H and SS1-4H wells were drilled and cemented to total depth using the Helmerich & Payne super-spec FlexRig Flex 3 land rig, with both laterals in the Mid Velkerri B Shale. The SS1-2H well encountered a downhole issue after drilling a 12,631 ft lateral, and a sidetrack drilled in early November 2026 delivered a usable lateral of 9,989 ft.

Timeline

  1. Early September: JS-DW1 well in the EP 161 permit spudded with the Ensign 971 land rig.

  2. October: JS-DW1 pilot hole reached total depth of about 11,300 ft.

  3. Early November 2026: SS1-2H sidetrack delivered a usable 9,989 ft lateral.

  4. Q4 2026: Beetaloo Joint Venture plans to stimulate the three SS1 wells.

  5. Q1 2027: SS1 wells are expected to be tied back to the Sturt Plateau Compression Facility.

Legal Context

The Beetaloo drilling proceeds under regulatory conditions set after the Northern Territory's 2017-2018 Scientific Inquiry into Hydraulic Fracturing. Progress on the SS1 wells extends that development path toward stimulation and production.

Residents and businesses in the Northern Territory may see further gas development activity as the SS1 wells move toward stimulation and tie-in. Production timing depends on stimulation results and tie-back work scheduled for the coming year.

The takeaway

Three completed wells mark an advance for the Beetaloo Basin, but the next measure of progress will be the stimulation results expected in late 2026.

What happens next

The Beetaloo Joint Venture plans to stimulate the three SS1 wells in Q4 2026, followed by tie-back to the Sturt Plateau Compression Facility in Q1 2027.