Coal Unavailability Tops 5.8 GW in Australia
Nexa Advisory's analysis of Australian Energy Market Operator data calls for enforceable coal retirement dates and a strategic reserve.
Updated on Nov. 24, 2026 in Energy

Live Poll
Do you think your local electricity reliability is getting better or worse?
Nexa Advisory reported that an average of 5.8 gigawatts of National Electricity Market coal generation capacity was unavailable in 2025, up from 5.3 gigawatts in 2024. Unavailable capacity represented 25.9 per cent of the market's coal fleet, and the firm recommended enforceable coal retirement dates and a strategic reserve.
Why it matters
Repeatedly extending the operating lives of coal-fired power stations undermines investment in replacement generation, storage and transmission. Nexa Advisory argues that uncertainty about retirement dates makes it harder to finance and deliver the infrastructure needed to keep the grid reliable across Australia.
Extreme wholesale price intervals in Victoria were almost five times more frequent when coal unavailability was high during periods of high residual demand, according to Nexa Advisory's analysis of Australian Energy Market Operator data. The report does not quantify how these conditions will change once the Yallourn power station closes in 2028.
The players
Nexa Advisory
Nexa Advisory is an energy analysis firm whose report on coal unavailability and retirement policy is the subject of this story.
Australian Energy Market Operator
The Australian Energy Market Operator runs the National Electricity Market and has proposed extending the coal closure notice requirement to five years.
Jess Wilson
Jess Wilson is the Victorian Opposition Leader who has promised to open the state to gas exploration and production.
The details
Nexa Advisory analysed Australian Energy Market Operator data and proposes procuring a strategic reserve around five years before scheduled closures where reliability assessments identify a material gap. Eligible resources could include new renewable generation, storage and virtual power plants. Under the current National Electricity Rules, generators must provide at least 42 months' notice of their initial closure date, unless granted an exemption, and the Australian Energy Market Operator has proposed extending that requirement to five years.
Timeline
2024: Unavailable coal capacity measured at 5.3 gigawatts.
2025: Unavailable coal capacity averaged 5.8 gigawatts.
2028: The Yallourn power station plans to cease operations.
Roadmap
The current National Electricity Rules require generators to give at least 42 months' notice of closure, and the Australian Energy Market Operator has proposed extending this to five years. Nexa Advisory's recommendations would move Australia further toward fixed coal retirement timelines as the grid transitions.
Households and businesses in Australia's National Electricity Market face price spikes when coal capacity is unavailable during high demand. Decisions on retirement dates will influence the reliability and cost of electricity supply across the country.
The takeaway
Reliable retirement timelines matter to energy users because they shape whether replacement generation and storage get built in time. Readers can follow how closure notice rules change as the Australian Energy Market Operator finalises its proposal.
Further reading
Explore more on Energy for background on Australia's grid transition.
Source note: This article includes information reported by Energy Magazine.