Amplitude Completes Annie-2 Gas Development Well

The Annie-2 well offshore Victoria was completed and cased as part of the East Coast Supply Project drilling campaign.

Updated on Nov. 11, 2026 in Oil and Gas

Isometric editorial illustration of a steel well-head rising from calm slate-blue sea beside a small offshore platform under a cream sky, evoking offshore gas development.
Amplitude Energy completed and cased its Annie-2 development gas well offshore Victoria on 28 October, reaching 2,253 metres, as part of the East Coast Supply Project. AI Illustration. Upload story photo >

Amplitude Energy has completed and cased its Annie-2 development well in permit VIC/L37 offshore Victoria, reaching a measured depth of 2,253m on 28 October. The well is being suspended ahead of planned development within the East Coast Supply Project.

Why it matters

Preliminary data indicates higher permeability, porosity and deliverability than the original Annie discovery, and the drilling programme is running ahead of schedule and budget. These results bear on the gas supply plans for the East Coast Supply Project.

Annie carries a gross 2C contingent resource estimate of 65 PJ, equivalent to 32.4 PJ net to Amplitude, based on the Annie-1 discovery. The Annie-2 well reached 2,253m and is about 10km north of the planned connection point to the CHN pipeline; final commercial output has not been confirmed.

The players

Amplitude Energy

Amplitude Energy is an Australian oil and gas company operating the Annie development within the East Coast Supply Project.

O.G. Energy

O.G. Energy is a partner holding a 50% interest in permit VIC/L37 alongside Amplitude Energy.

The details

Annie-2 underwent clean-up operations on 9 and 10 November, and operations were expected to finish during the week of the announcement. Gas composition samples are consistent with those from the original Annie discovery, and no part of the general contingency for the drilling programme has been used. The Transocean Equinox rig is due to move to the Nestor exploration prospect for the final well in the campaign.

Timeline

  1. 2019: Annie-1 well discovers gas in the Waarre C reservoir.

  2. 28 October 2026: Annie-2 reaches a measured depth of 2,253m.

  3. 9 and 10 November 2026: Annie-2 clean-up operations are conducted.

  4. September 2026: Amplitude reaches final investment decision on the ECSP development phase.

  5. Calendar year 2028: First gas is targeted for the East Coast Supply Project.

Market Landscape

The Annie-2 result extends the East Coast Supply Project drilling campaign, which is designed to add gas supply for Australia's east coast market. Confirmed reservoir quality at Annie strengthens the project's development case ahead of first gas in calendar year 2028.

The Annie development is part of the ECSP plan to add gas supply to Australia's east coast, which could affect future domestic gas availability. Households and businesses will not see any direct change until first gas is delivered, currently targeted for 2028.

The takeaway

Higher reservoir quality at Annie-2 suggests the ECSP development may deliver more gas than the original discovery indicated. Readers tracking east coast supply should watch for final production rates and the commencement of first gas.

What happens next

Annie-2 operations are expected to finish during the week of the announcement, and the Transocean Equinox rig is due to move to the Nestor exploration prospect for the final well in the ECSP campaign.

Further reading

Explore more Oil and Gas developments shaping Australia's east coast gas supply.

Source note: This article includes information reported by Offshore Technology.