Energy Equipment Delays Forced Asset Reuse
Supply chain constraints have compelled Australian energy companies to modernise and redeploy existing power generation assets.
Updated on Oct. 14, 2026 in Energy

Live Poll
Do you expect the shift to new energy sources to increase your household electricity costs?
Extended lead times for new equipment have forced Australian energy firms to prioritise the modernisation and relocation of existing power plant assets. Companies are currently moving turbines from remote mine sites to new regions to sustain grid stability.
Why it matters
The shift toward reusing existing infrastructure is driven by wait times of up to eight years for new generation equipment. These measures aim to maintain system strength as the nation transitions its energy grid and prepares for future station closures.
New synchronous condensers require up to five years for delivery, while gas turbine procurement can take as long as eight years. Modernising existing power station control systems can improve operational performance by a small percentage.
The players
Origin Energy
This major Australian energy company provides electricity and natural gas to millions of customers and manages several large-scale power generation facilities.
Transgrid
This entity manages the high-voltage electricity transmission network across New South Wales and the Australian Capital Territory.
AEMO
The Australian Energy Market Operator is responsible for managing the nation's electricity and gas systems to ensure reliable energy delivery.
ABB
This multinational corporation specialises in electrification and automation technologies, including critical control systems for power station operations.
The details
Australian energy companies are relocating gas turbines from remote mining operations to other regions to meet growing demand. Simultaneously, operators are focusing on control system upgrades to improve the longevity and cybersecurity of existing power plants.
Timeline
Transgrid began assessing system strength requirements in 2021.
AEMO published the Transition Plan for System Security in 2025.
AEMO expects a third iteration of the security plan before the end of 2026.
Origin Energy has scheduled the closure of the Eraring Power Station for April 2029.
Deeper Dive
The current strategy of redeploying existing power assets directly supports the grid reliability objectives established in the AEMO's Transition Plan for System Security.
By extending the lifespan of existing power assets, companies aim to prevent potential shortfalls in grid strength that could otherwise impact supply reliability. This focus on modernisation helps maintain stability during the transition away from coal-fired plants like Eraring.
The takeaway
Supply chain constraints have fundamentally changed how energy firms approach grid management, prioritising the clever reuse of older infrastructure over new builds. Consumers should expect these infrastructure-focused strategies to continue as the national energy grid undergoes a period of significant technical transition.
What happens next
AEMO is scheduled to release the third iteration of its Transition Plan for System Security before the end of 2026.
Further reading
For more information on national power stability, visit the Energy section.
Source note: This article includes information reported by RenewEconomy.