GCC AI Growth Hinges on Power and Housing
A Submer report finds Gulf AI ambitions are constrained by grid capacity and infrastructure operation rather than investment or chip access.
Updated on Nov. 27, 2026 in Data Centers

Live Poll
Do you think your area's data centre growth will raise your utility bills?
Submer's GCC AI & HPC Infrastructure Report finds that the Gulf Cooperation Council's AI ambitions are limited by power, housing and infrastructure operation rather than by investment or chip access. The regional data centre pipeline exceeds US$93 billion across more than 174 tracked projects.
Why it matters
Securing grid capacity takes longer than building the physical site, so power and heat constraints shape delivery timelines and operating costs. The report positions the region as a potential sovereign AI and export-compute hub for the Middle East and Africa.
A single NVIDIA GB300 NVL72 rack draws roughly 132 to 135kW, peaking near 155kW, with ambient temperatures above 40°C adding cooling demands. Direct-to-chip cooling accounted for 42.85% of liquid-cooling revenue in 2025, while the report does not quantify how these loads will be met at scale.
The players
Submer
Submer is a liquid and immersion cooling company headquartered in Saudi Arabia that publishes infrastructure research on data centre thermal management.
HUMAIN
HUMAIN is a Saudi AI company planning large-scale GPU deployments as part of the kingdom's artificial intelligence ambitions.
G42
G42 is an Abu Dhabi-based artificial intelligence company that received authorised NVIDIA Blackwell chip exports from the United States.
The details
The report says closed-loop thermal solutions can achieve zero direct water consumption under extreme heat, and immersion cooling supports densities above 100kW per rack with PUE levels of 1.02 to 1.03. Saudi data centres reportedly consumed around 15 billion litres of water in 2024, and HUMAIN plans to deploy up to 600,000 NVIDIA GPUs over three years.
Timeline
November 2025: The United States authorised exports of up to 35,000 NVIDIA Blackwell chips each to HUMAIN and G42.
2024: Saudi data centres reportedly consumed around 15 billion litres of water.
2026-2027: First large-scale AI capacity is expected to enter production.
2028-2030: The GCC is expected to mature into a sovereign AI and export-compute hub.
The Tech Race
The November 2025 US authorisations of up to 35,000 NVIDIA Blackwell chips each to HUMAIN and G42 gave Gulf operators chip access, shifting the bottleneck to power and infrastructure. The report indicates that the race for AI capacity in the region now depends on grid capacity and heat management rather than on export licences.
Constraints on grid power and cooling may affect the availability and pricing of cloud AI services that rely on Gulf data centres. Developers and enterprises depending on regional AI capacity should expect delivery timelines to track infrastructure build-out rather than chip supply.
The takeaway
Gulf AI capacity will likely depend more on securing grid power and managing heat than on acquiring chips or capital. Organisations planning regional AI deployments should weigh power availability and cooling design alongside hardware access.
Further reading
Explore more on Data Centers to see how power and cooling shape AI infrastructure worldwide.
More information
Read the full GCC AI & HPC Infrastructure Report published by Submer.
Source note: This article includes information reported by TahawulTech.