Afghanistan Nears Water Diversion for Qosh Tepa Canal

Afghan authorities are preparing to divert Amu Darya water into the canal, while Uzbekistan says full withdrawal will not begin before 2030.

Updated on Nov. 26, 2026 in Utilities

Isometric editorial illustration of a steel sluice gate set into an earthen embankment, with a straight dry canal running across arid steppe toward a river.
Afghan authorities are preparing to divert Amu Darya water into the Qosh Tepa Canal, while Uzbekistan says full withdrawal will not begin before 2030. AI Illustration. Upload story photo >

Afghanistan is preparing to begin diverting water from the Amu Darya into the Qosh Tepa Canal, with second-stage earthworks reported 99% complete. The Afghan side has not specified when deliveries will start, the planned withdrawal volumes, or whether agreements have been reached with downstream countries.

Why it matters

The canal is intended to irrigate 500,000-600,000 hectares and expand agricultural output, but Uzbekistan and researchers warn it could intensify water shortages across Central Asia. Downstream concerns center on how much water will ultimately be taken from the shared river.

The canal is 285 km long with an estimated construction cost of US$680 million, rising to about US$1.5 billion with irrigation networks included according to researchers. A May 2026 University of Oulu study projected that diverting 20% of the Amu Darya's flow could cut more than 1.2 billion cubic metres from Uzbekistan's Kashkadarya region by 2030, though the final withdrawal volumes remain unconfirmed.

The players

National Development Corporation (Afghanistan)

The Afghan state entity that reported the canal's second-stage progress and the plan to direct water from the Amu Darya into the main intake and canal.

Uzbekistan Water Resources Ministry

Uzbekistan's ministry whose minister has disputed the canal's capacity figures and stated that full-scale withdrawal would not begin before 2030.

The details

The second stage of the canal includes construction of the main intake facility, along with work on 47 bridges and water flow regulation structures. Afghan authorities selected a water intake site in the Kaldar area instead of a higher-elevation site proposed by experts, citing initial costs and logistical considerations.

Timeline

  1. October 2023: The first 108 km section of the canal was completed.

  2. November 2023: The area flooded by a leak in Balkh province was measured at 450 hectares.

  3. April 2025: The flooded area from the Balkh leak expanded to 2,400 hectares.

  4. 2030: Earliest date for full-scale water withdrawal, according to Uzbekistan's Water Resources Minister.

  5. November 25, 2026: Second-stage earthworks were reported nearing completion.

Big Picture

The Qosh Tepa Canal's ongoing construction follows the Balkh leak documented in satellite imagery, where flooding grew from 450 hectares in November 2023 to 2,400 hectares by April 2025. That record shows the structural risks of the project as diversion from the Amu Darya moves closer.

For households and businesses far from the canal, the project's effects would appear mainly through water availability and agricultural trade rather than direct costs. Residents in downstream regions such as Uzbekistan's Kashkadarya could face reduced water supply for farming and domestic use if projected withdrawals materialize.

The takeaway

Large upstream water projects can reshape supply for countries that depend on the same river, so the timing and volume of withdrawals matter as much as the canal's design. Watching for announced withdrawal volumes and any agreements with downstream states will show how the project's impact develops.

Further reading

For related coverage of water infrastructure and supply, explore the Utilities section.

Source note: This article includes information reported by UzDaily.