Marimaca Copper Lines Up $450 Million Financing
Sprott Resource Lending has signed a non-binding term sheet with the Chilean copper developer for up to $450 million.
Updated on Nov. 24, 2026 in Corporate Finance

Marimaca Copper signed a non-binding term sheet with Sprott Resource Lending for up to $450 million in financing, including $425 million in senior secured debt and an equity investment of up to $25 million from Sprott. The first $100 million of the loan becomes available after a construction decision.
Why it matters
The financing would fund the Marimaca oxide project in northern Chile, which is estimated to cost $587 million to build and would give the company a path toward production. For international investors and the copper sector, the deal shows how developers are securing capital for mining projects that depend on debt with a minimum interest rate of 8.5%.
The loan carries a minimum interest rate of 8.5%, with Sprott charging 5.75 percentage points over the secured overnight financing rate and a 2.75% floor on the benchmark. The term sheet is non-binding, and the final investment decision is not expected until mid-2027.
The players
Marimaca Copper
Marimaca Copper is a Vancouver-headquartered copper developer whose main project is in northern Chile, and its shares trade in Toronto.
Sprott Resource Lending
Sprott Resource Lending is a specialty lender in the natural resources sector that provides debt and structured financing to mining companies.
The details
The planned open-pit operation would use heap leaching to recover copper from the Marimaca oxide project, about 45 km from Antofagasta, Chile. The project is expected to produce an average of 43,000 tonnes of copper cathode a year over 13 years, and it benefits from proximity to highways, power lines and the port of Mejillones.
Timeline
Marimaca received environmental approval for the oxide project in November 2025.
Marimaca reported $127 million in cash and equivalents at Sept. 30.
Principal repayments on the loan would begin on March 31, 2031.
A targeted final investment decision on the project is expected in mid-2027.
Market Dynamics
Structured, staged debt from specialty resource lenders has become a common way for junior copper developers to fund construction without a full equity raise. The Marimaca package follows that pattern, releasing only the first $100 million after a construction decision while tying repayment to a floor-protected interest rate.
For shareholders, the financing package signals that Marimaca can fund construction with debt rather than dilutive equity, though the non-binding status means the terms are not yet locked in. Retail and institutional investors tracking copper developers should watch whether the company converts the term sheet into a binding agreement ahead of the 2027 decision point.
The takeaway
Staged financing that releases capital only after a construction decision lets developers limit exposure before a project is fully committed. Readers following copper supply should track whether the Marimaca term sheet becomes binding and whether the 43,000-tonne production target holds.
What happens next
A targeted final investment decision on the Marimaca oxide project is expected in mid-2027, and the first resource estimate for Pampa Medina is expected in the first half of 2027.