Namib Minerals Pours First Gold at Redwing
The Nasdaq-listed company restarted a century-old Zimbabwean gold mine after a seven-year hiatus.
Updated on Nov. 23, 2026 in Corporate Finance

Namib Minerals has poured its first gold at the Redwing mine in eastern Zimbabwe, a century-old site that had been on hiatus for seven years. The company plans a staged ramp-up of production at Redwing in 2027.
Why it matters
The restart adds to Namib Minerals' operating footprint alongside its How Mine in Bulawayo and its planned Mazowe Mine asset. For international investors and observers, it marks a step in the company's effort to build a larger gold production base in Zimbabwe.
Shares fell 2.29% to $0.6 mid-day Monday in New York, giving the company a valuation of $33.7 million. The Definitive Feasibility Study is described as fully funded, with its conclusion expected in the first quarter of 2027.
The players
Namib Minerals
A company listed on Nasdaq under the ticker NAMM that owns and operates the How Mine in Bulawayo and is pursuing the Redwing and Mazowe Mine assets in Zimbabwe.
The details
Mine infrastructure and processing facilities at Redwing were rehabilitated and recommissioned through a phased restart. The company expects to spend $300 million on mine restarts, and a Definitive Feasibility Study is set to inform further steps.
Timeline
Redwing produced about 650,000 ounces of gold between 1981 and 2023.
The How Mine produced 25,000 ounces of gold in 2025.
Shares traded down mid-day on Monday, November 23, 2026.
Targeted increase in ore processing and gold production is planned for 2027.
The Definitive Feasibility Study is expected to conclude in the first quarter of 2027.
Corporate Finance Context
The Redwing restart follows a pattern of reviving older Zimbabwean gold operations instead of developing greenfield sites. The company's plan to combine Redwing, How Mine and Mazowe into a 300,000-ounce annual base reflects a consolidation strategy in the region's gold sector.
For shareholders, the outcome depends on whether the restarts reach the targeted production and whether the $300 million spending plan holds. The Definitive Feasibility Study's conclusion in early 2027 will be the next checkpoint for assessing that progress.
The takeaway
Restarting older mines can add production quickly, but investors should track whether cost estimates and staged timelines hold as projects move from feasibility into operation.
What happens next
The Definitive Feasibility Study is expected to conclude in the first quarter of 2027, and a staged increase in ore processing and gold production is targeted for 2027.
Further reading
Explore more on Corporate Finance for context on how mining companies raise and deploy capital.
Source note: This article includes information reported by MINING.



