Mitsubishi Heavy Says Data Centers Will Turn to Grid
Mitsubishi Heavy Industries' CEO argues off-grid data center costs will push operators to connect to utility power networks.
Updated on Nov. 23, 2026 in Data Centers

Live Poll
Do you expect your electricity bills to rise because of data center demand?
Mitsubishi Heavy Industries CEO Eisaku Ito said on November 6 that off-grid data center plans, which often rely on smaller gas-fired plants, will prove costlier than utility-scale generation. Utilities and independent power producers accounted for 94% of the company's new gas turbine orders in 2024 and 2025.
Why it matters
Data centers account for around 10% of U.S. total electricity demand, so where their power comes from shapes grid planning and gas turbine supply. Ito's view suggests the AI buildout may lean on utility grids rather than standalone power systems.
Mitsubishi Heavy booked 8 GW of large frame gas turbine orders in the first half of fiscal 2026, against 16 GW for all of fiscal 2025. Whether the company's expected 70 GW-per-year global turbine demand materializes over the next five years remains unconfirmed.
The players
Mitsubishi Heavy Industries
A major Japanese industrial conglomerate that manufactures gas turbines, aerospace equipment and energy systems for utilities and power producers worldwide.
Eisaku Ito
The chief executive of Mitsubishi Heavy Industries who leads the company's energy and turbine strategy and spoke to analysts on the November 6 call.
The details
Ito told analysts that many U.S. data center operators' off-grid plans depend on smaller gas-fired plants that cost more to run than the larger utility and independent power producer plants now being built. He also said Mitsubishi Heavy vets new orders carefully and has recorded no order cancellations in the past two years, while the company plans to double its gas turbine production capacity by 2030.
Timeline
2024 and 2025: Utilities and independent power producers made up 94% of Mitsubishi Heavy's new gas turbine orders.
November 6: Ito made his comments on the analyst call.
Fiscal 2025: Mitsubishi Heavy booked 16 GW of large frame gas turbine orders.
First half of fiscal 2026: The company booked 8 GW of large frame gas turbine orders.
May 2027: Mitsubishi Heavy is expected to release additional details on its new business plans.
The Tech Race
Data centers now draw around 10% of U.S. electricity demand, and Mitsubishi Heavy's comments suggest that load will be served mainly through utility grids rather than stand-alone gas plants. The shift positions gas turbine makers against rivals competing for the same utility and independent power producer orders.
If data centers connect to utility grids rather than building their own power, local electricity rates and grid capacity planning could be affected for households in those regions. Consumers may see the cost of AI-driven demand reflected in utility bills over time.
The takeaway
Where data centers source their electricity may matter as much as how many they build, since grid connection shifts costs and planning burdens onto utilities. Tracking turbine orders offers an early signal of how that trade-off is resolving.
What happens next
Mitsubishi Heavy Industries is expected to release additional details on its new business plans in May 2027.
Further reading
Explore more on Data Centers to see how AI buildout is reshaping power demand.
Source note: This article includes information reported by Utility Dive.