Primetals Upgrade Lifts Shougang Hot Strip Mill

Primetals Technologies completed a Level 2 automation upgrade at Shougang Qian'an Hot Strip Mill No. 1, and the mill has since exceeded agreed performance targets.

Updated on Nov. 20, 2026 in Manufacturing

Bold flat-color editorial illustration of a single glowing steel coil resting on rollers in deep red and cream, evoking an industrial steel mill upgrade.
Primetals Technologies completed a Level 2 automation upgrade at Shougang Qian'an Hot Strip Mill No. 1 in China, and the mill has since exceeded agreed performance targets. AI Illustration. Upload story photo >

Primetals Technologies received final acceptance for a Level 2 automation upgrade at Shougang Qian'an Hot Strip Mill No. 1 in China. The upgraded mill exceeded its agreed performance targets, and Shougang Qian'an plans further work under an Electrics and Automation service agreement.

Why it matters

The project shows that automation modernization can be commissioned within a scheduled maintenance shutdown without extending the mill's downtime. For steelmakers weighing similar upgrades, the result offers a reference point on how quickly output can recover after commissioning.

The mill returned to around 90% of average daily output within five production days and reached full capacity ten days after its first coil was rolled following a 10-day annual maintenance shutdown. Four weeks of shadow-mode operation preceded production, and the stub does not disclose the specific performance targets exceeded.

The players

Primetals Technologies

A global industrial technology company headquartered in London that supplies metals production equipment and automation systems to steelmakers worldwide, with approximately 7,000 employees.

Shougang Qian'an Iron & Steel Co.

The steelmaking operator that runs Hot Strip Mill No. 1 at its Qian'an site in China and commissioned the automation upgrade with Primetals.

The details

The project covered Level 2 system modernization and selected Level 1 functions across the reversing roughing stands, six-stand finishing mill, sizing press and coil box. It added an expanded material database, the Contour and Flatness Optimizer, and a Diagnostic Plug giving process engineers earlier access to production and quality data. Primetals and Shougang engineers worked together on modelling, commissioning and production preparation, and Shougang later presented Primetals with a formal letter of thanks.

Timeline

  1. Level 2 commissioning was completed during the mill's 10-day annual maintenance shutdown.

  2. The upgraded system ran in shadow mode for four weeks before production.

  3. The mill reached around 90% of average daily output within its first five production days.

  4. Full production capacity was reached ten days after the first coil was rolled following the shutdown.

Manufacturing Context

The upgrade applies Primetals' Level 2 hot strip mill automation platform to an existing Chinese installation, extending a model in which control-system modernization is completed during scheduled maintenance rather than through extended shutdowns. The follow-on service agreement signals that the supplier relationship is continuing beyond this single project.

For steel producers, the project demonstrates that Level 2 automation can be installed and brought to full output within a 10-day maintenance window, shortening the production gap that often follows control-system upgrades. Operators considering similar retrofits can use the reported ramp-up figures as a planning benchmark.

The takeaway

The project shows that automation upgrades on large industrial lines can be scheduled so that production returns quickly after commissioning. The reported ramp-up gives other steelmakers a concrete timeline to weigh against their own maintenance calendars.