Eldorado Commissions First Two Skouries Filter Presses

Filter presses at the Skouries mine in northern Greece are being brought online as the operation advances toward commercial production.

Updated on Nov. 20, 2026 in Manufacturing

Bold flat-color editorial illustration of stacked steel filter-press plates in a rectangular frame, with a pipe feeding a grey slurry cake edge, evoking industrial mine tailings dewatering.
Eldorado Gold brought the first two of six Metso filter presses online at its Skouries mine in northern Greece on November 20, 2026, as it nears commercial production. AI Illustration. Upload story photo >

Eldorado Gold has commissioned the first two of six Metso tailings filter presses at its Skouries mine in northern Greece, with five units operating and one installed as a spare. The plant is operating continuously while commissioning and ramp-up activities continue across the site.

Why it matters

Four operating filter presses are required to support commercial production of sulphide ore, making the commissioning schedule a key milestone toward full-scale output. Filtered tailings are central to Skouries' Integrated Extractive Waste Management strategy.

Skouries is projected to average 140,000 oz of gold and 67 million lb of copper annually over its life of mine. Commissioning of the remaining four filter presses is expected by year end, though the precise completion timing is not specified.

The players

Eldorado Gold Corp.

Eldorado Gold is a Canadian gold mining company with operations in Turkey, Greece and Canada, and is the developer and operator of the Skouries project.

The details

The filter presses are being commissioned progressively as throughput at the plant increases. Eldorado Gold reported the first two units operational on November 20, 2026, with the remaining units scheduled to follow.

Timeline

  1. November 20, 2026: Eldorado Gold reports first two filter presses operational.

  2. Year end 2026: Commissioning of remaining four filter presses expected to be completed.

Industry Context

Dry-stack filtered tailings, as deployed under Eldorado's Integrated Extractive Waste Management strategy at Skouries, represent a shift away from conventional wet tailings dams in the mining sector. The commissioning of filter presses at Skouries marks this approach moving from design into operation.

Full commissioning of the remaining filter presses by year end will determine when Skouries reaches commercial sulphide production. Readers tracking gold and copper supply should watch for that milestone in the coming months.

The takeaway

Watch for the completion of the remaining four filter presses at Skouries, as that milestone gates commercial sulphide production. Tailings management milestones like this are an early indicator of whether new mines can meet environmental commitments on schedule.

Further reading

Explore more industrial operations coverage in the Manufacturing section.

Source note: This article includes information reported by Engineering and Mining Journal (E&MJ).