WSP Settles Iron Mountain Frankfurt Data Center Suit
WSP agreed to pay roughly $17 million to Iron Mountain over incomplete design work on a Frankfurt data center.
Updated on Nov. 19, 2026 in Data Centers

In January 2026, engineering firm WSP agreed to pay Iron Mountain roughly $17 million after mediation of a breach-of-contract suit filed in New York federal court in 2023. Iron Mountain alleged that WSP's work on a Frankfurt data center was incomplete and error-ridden, delaying the project and adding costs.
Why it matters
The dispute shows how design deficiencies on large data center builds can ripple into costly litigation among developers, designers and their sub-consultants. For operators planning facilities in Europe and the US, it underscores the value of contingency planning and clear accountability in design contracts.
The 320,000 sq ft of data center space was spread across three building modules, including 19,000 sq ft of data halls covered by the design work. Iron Mountain's roughly $20 million contingency compares with a typical contingency of about $1.1 million for a project of similar magnitude, and WSP's pending claim against AECOM seeks a similar $17 million.
The players
WSP
WSP is a global engineering and professional services firm that provided the design work for the Frankfurt project.
Iron Mountain
Iron Mountain is a Portsmouth, New Hampshire-based data center and storage company that commissioned the Frankfurt facility.
AECOM
AECOM is a global infrastructure consulting firm that provided engineering design services on the project and is the target of WSP's claim.
The details
Iron Mountain hired WSP in 2019 to design a four-story building shell for a Frankfurt data center. By March 2020, the design delivered was incomplete and error-ridden, and Iron Mountain alleged that WSP's actions and those of its sub-consultants delayed completion and increased costs. WSP denied the allegations and brought a claim against AECOM, which had provided engineering design services on the project.
Timeline
2019: Iron Mountain signs WSP for Frankfurt data center design.
February 2020: Target date for Iron Mountain's contractor contract signing.
March 2020: Design deliverable found incomplete and error-ridden.
2023: Iron Mountain files breach-of-contract suit in New York federal court.
January 2026: Mediation produces roughly $17 million WSP settlement.
Market Landscape
Data center construction has grown rapidly across Europe and the US, raising the stakes of design errors on multi-hundred-thousand-square-foot builds. The parallel WSP claim against AECOM in a UK court shows how liability for such failures is often spread across several firms in the supply chain.
For businesses that rely on cloud services and storage, construction delays at data center facilities can affect the capacity and pricing those providers offer. The case highlights that design failures can extend project timelines and costs, factors that may influence the availability of hosting services over time.
The takeaway
Design quality is foundational to large data center projects, and disputes over it can run for years across multiple courts and firms. Organizations commissioning such facilities benefit from precise contract terms, realistic contingencies and clear lines of accountability among designers.
Further reading
Explore more on data centers and how large facilities are being built and financed.
Source note: This article includes information reported by Engineering News-Record (ENR) magazine.