NKT is widening its Boka Constructor cable-lay barge by eight meters, from 32 to 40 meters, to convert the former Boskalis vessel into a nearshore cable-layer. AI Illustration. Upload story photo >

NKT has widened the Boka Constructor cable-lay barge by eight meters, expanding it from 32 meters to 40 meters as part of its conversion to a nearshore cable-laying barge. The vessel, bought from Boskalis in 2025 and renamed NKT Isabella, is set to join NKT's marine installation fleet next year.

Why it matters

The widening creates space for cable handling equipment while keeping the draft low enough for ultra-shallow water operations. The conversion expands NKT's capacity to install cables in shallow coastal areas.

The barge is 126 meters long, and its accommodation has grown from 50 to 73 persons. Once fully equipped, its three cable turntables will hold a combined 6,000 tons, though the completion timeline beyond 2027 is not detailed.

The players

NKT

NKT is a Danish cable manufacturer and installer that supplies power cables for offshore wind and grid projects worldwide.

Boskalis

Boskalis is a Dutch marine contractor known for dredging, offshore construction and heavy marine transport services.

The details

The Boka Constructor was built in 2016 at Gdynia/Swinemünde and has been renamed NKT Isabella following its purchase from Boskalis. Work to widen the hull and add modifications is underway in 2026, with the vessel scheduled to join the fleet next year.

Timeline

  1. October 2025: NKT reports investing in the Boka Constructor barge.

  2. 2026: Widening and modifications are underway.

  3. 2027: The barge is set to join NKT's marine installation fleet.

Industry Landscape

The conversion adds shallow-water capability to the cable-laying vessel fleet that connects European offshore wind farms to shore. Vessels able to operate in ultra-shallow water are needed for the nearshore segments of these grid connections.

The added vessel capacity may help shorten installation timelines for offshore and coastal grid connections. Electricity customers ultimately bear these infrastructure costs through their power bills, though the extraction does not quantify any effect.

The takeaway

Specialized vessels such as cable-laying barges are a bottleneck for grid expansion, so capacity additions like this one matter for how quickly power projects reach customers. Watch for the barge's entry into service in 2027 as a measure of NKT's added installation capacity.